Change Orders - Miramontes - 1998-03-06 Costa Mesa Sanitary District CONTRACT CHANGE ORDER NO 1 PROJECT #140, #145 Reconstructing Various Sewer Lines TO Miramontes Construction Co Inc Contractor You are hereby directed to make the herein described changes from the plans and specifications, or do the following work not included in the plans and specifications on the contract. Note: This change order is not effective until approved pursuant to adopted District policy Change Requested by Costa Mesa Sanitary District A r Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. 1 Delete Bid item 11 (line on Pegasus Street was repaired by others during County storm drain project) Bid item 11 was for $1 700 2 Add 10 days to contract length due to City storm drain project in 19th Street and Anaheim delaying work New last day of work is April 21 1998 Net Increase ❑ Decrease ® in Contract $1 , 7nn By reason of this order the time of completion will be adjusted as follows. 10 additional days Robin B Hamers 2/17/98 Prepared by Date A Approved.by • Robin B Hamers t Date 2/17/98 Distr'ct En ee Approved by District Manager Date '417)913 Required whe I e oft $1,000 more • Board approval also needed when increase in cost exceeds 2% of contract or $1,000 whichever is greater We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment,furnish all materials,except as may otherwise be noted abov and perform all services necessary for the work above specified,and will accept as full payment therefor the prices shown ahoy Date l''accepted , �/�'/3/06/98 Contractor T1iramontes Cnnstrnrti on Co Trir By t"'IMW40- `r,Y IA_bl4t_t21 Title Vice President U CMF 1082-68 White-0'5R ct File Ca ry-Contr cto Copy- Pink-Fi Golde od-Engi Costa Mesa Sanitary District CONTRACT CHANGE ORDER NO 2 PROJECT #140, #145 Reconstructing Various Sewer Lines Miramontes Construction Co Inc TO Contractor You are hereby directed to make the herein described changes from the plans and specifications, or do the following work not included in the plans and specifications on the contract. Note: This change order is not effective until approved pursuant to adopted District policy Change Requested by Costa Mesa Sanitary District 0 Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. Additional repair location needs to be added to project. New location discovered by District cleaning crew when high pressure hose would not pass through pipe New location is at sewer station 8+80 and is 65 feet easterly of bid item 1^ of project New work to be same price as bid item 12 Net Increase © Decrease El in Contract $ 1.900.00 By reason of this order the time of completion will be adjusted as follows. None Prepared by Robin B Hamers Date 2/20/98 Approved by Robin B Homers taf Date 2, 20/98 Distr'ct Engineer Approved by District Manager Date 9 /1° /419 Requ' ad whe in e in cost Is $1,000 mo • Board approval also needed when increase in cost exceeds 2% of contract or $1,000, whichever is greater We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials,except as may otherwise be noted above,and perform all services necessary for the work above specified,and will accept as full payment therefor the prices shown above. 3/06/98 Miramontes Construction Co Inc Date accepted ' / � ,.,,,� ��y Contractor By t II AA_�%�t-.Q1 .2 Title Vice President CMF 1082-68 White-Dish ct File Ca ry-Contr cto Copy Pink-Finan Gold° od.Engin 1/4%. Costa Mesa Sanitary District CONTRACT CHANGE ORDER NO 3 - PROJECT #140, #145 .Reconstructing Various Sewer Lines TO Miramontes Construction Co Inc Contractor You are hereby directed to make the herein described changes from the plans and specifications, or do the following-work not included in the plans and specifications on the contract. Note: This change order is not effective until approved pursuant to adopted District policy Change Requested by Costa Mesa Sanitary District st Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. Contractor unable to complete bid item #4 -nterfering water line and storm drain prevented access to pipe Contractor due 4 hours for excavat on and backfill. .ng time Distri:t to instal.] Link Pipe at a later date Excavation time cf 4 hrs ( lee attached) = $1 564 89 Delete bid item #.f = (1 700.00) Net change ( 135 11) Net Increase El Decrease fxl in Contract $ 135 l 1 By reason of this order the time of completio }.ryill be adjusted as follows. Nonn Prepared by Robin B. HEmers Date 3/3/198 Approved by Robin B. H^mcrs District E (.10 Date - ,/3/98. Approved by District Manager i ' .P Date 51,h8 Requ eat whe n r ate ' cost $1,000 mo / • Board approval also needed when increase in cost exceeds 2% of contract or $1,000 whichever is greater We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment,furnish all materials except as may otherwise be noted above,and perform all services necessary for the work above specified,and will accept as full payment therefor the prices shown above. Date acr,-pted 3 0619$ Contractor Mi ramonte: Cons rtict- on Co Inc I By ...in. (1 ZJ/" ° Title Vice President CMF 1082-68 White-Distr ct File Ca ry-Contr cto Copy-Pink-Fi Golds oat-Engi / ' �I {� f O N Co CO ,--1� ° 1 N M CO O a N- w z= ° W O 617 .t y O en on co Co N 0% N iD a CO 4-1 - .t -t CO .M-- � O 0 � ' L IL O F U m .1 y a • < < CO m < U C a x a JY 0 ON ' r F Z 1' Y F a m t<� 0 F C O ° G a a _[o v1 uy M O 0 It 4 O Z 7 id O O d M M 'o a a • ► t• I < Z c, O y y U U ..1 a Z Z. i O 4 4 ¢ I V - r r . 4 2 O b a p F " n, as O 3 O O u • u • u u • o • u • u u = x a a . t 0 O y Y W 1- W W Y '7 Y r y '. W 0 F G o c o U o oio c a 0 a o a o c o c o a M a a o m • % C n 1 O Z + I 1 ' 4 a 2 PI 1 Iy P I 14 Z Z O a C 4#1!‘ 1� U •F a B i 1 ` p^ I p 4 O Y o°o1 -' c2 Y� G � y I � o ER o t I C ` �� �ny`l� ` 1 O 1f1 Z H • V 1C Y �{ o ♦ w C I C 4i 4 Y •1 i \ 1 SS J11 \ \ N ' y Y Y p W J \ n\ ` (�,\ 5 1.1 a s �' `(\ y x y Y J \ O `. .J c •F y D a [ Z rn Q N a•i 0 a a f 3 =I iI a : y ° U I- \ O 100 00 Oo 00 0 0 i oo CN co r V 0 : 0 0 0 0 0 0 0 0 O 0 cri O N W X Ox! w E W �� '--1 r o• Z l \\ i Z I IO O m aD O .Y O ^-i 01 N .-I 0 J n` Ya �T CO 1^1 <+1 .t co N 0 t'1 N N. C H 1 ., y O O O 0 O 0 0 0 k�,`F IO0 0 0 0 0 0 0O _ i I = •• a, 4 v---.2?Th tqq ^ \v aiM ,4 N c Ca -4 O '0 0 D N Z ^ 3 x • 0 < 1 [ Z L O BBC I- N 43 Z 2,1 .a n = II a. i j • A v Z Ps 2 ha v r m a ii 16 NI 3 4 >f-\) ? d ' ,e ,- 'N a ?. ■ W a _ çqn • • �\I\ � \ � �I I H=n x !! SO GAITAN TRUCKING CAL-T-124397 P 0 BOX 7164 ORANGE CA 92613 ( 714) 998-3469 FAX ( 714) 998-7509 Page 1 Date 02/07/98 Invoice 02-002 MIRAMONTES CONST CO INC P 0 BOX 90095 CITY OF INDUSTRY CA 91715 Work Freight Hr/Ton Date Bill Description ( Material Loads Rate Total 02/02 768916 COSTA MESA JOB 8 00 60 00 480 00 02/04 768917 COSTA MESA JOB 4 50 60 00 270 00 02/05 768918 COSTA MESA JOB 8 00 60 00 480 00 02/06 768919 COSTA MESA JOB 2 00 60 00 120 00 GROSS 1 350 00 *****THANK YOU***** �j 1928 b MIRAMONTES CONST. CO. INN I CAM *z arA x u r , INVOICE No ' „'38742 4'2/1.a: /-�PE inkaal\ " \\ COMPANY P 0 Box 4609 Anaheim, CA 92803 1801 Penhall Way TO MIRAMONTES CONSTRUCTION P 0 BOX 90095 CITY OF INDUSTRY CA 91715 UESTIONS REGARDING THIS INVOICE, PHONES 714-772-6450 OUST NO. 31995 PH. 818-330-1043 ATE DIVISION JOB NO. JOB I . 'ST PO NUMBER HRLY WILSON AND COLLEGE COSTA MESA V-MARY AN 2/12/98 001 TICKET. RTPTTON_.. _ - MR nATP& _NIIPR. . . r Or/_,__.__—P_RLE__ eNOUN-T• FLATSAW OVER 10" 2/05/98 150962 2. 00 128. 00 256. 00 FLATSAW UP TO 10" 2/05/98 150962 5. 50. 106'. 00 583. 00 FLATSAW- UP TO .10" ,I.., tr &; INVOICE AIK MAKE REMITTANCE TO INDUSTRIAL ASPHALT P 0 BOX 2950 LOS ANGELES, CA 90051 INDUSTRIALASPHALT FED-I [I': S5-CE457SC CUSTOMER NO 500Clo INVOICE NC 1537f31 SOLO T0. INVOICE DATE C1/27/9f DELIVERY MIRAMONTES CCM3TR CO DATE C1/21/9E F 0 G1X 92345 SIT! JF IADUSTRY. CA 91715 PLANT SANTA AlP TELEPHONE 714/544-0422 TERMS.NET 10th JOB REFERENCE: Foe-DUBLIN 1 WATSON JCCSTA MESA '�w y' .. .. q +..,y,RC: -1i.^ ...t . .b ..x»vt'rr.^.uka[: ..rt...., r, tr.. ,.. _ -• r .. .. °{,. r ITFM 9y 'F ' lR. tUNIT �'}, l]UANTRY OR TIME'i«-4 i �UNRPFitCE< COLD MIX SCSJJ TON 5.GC zS_Ct 14-5.CC 7_750C Y SALES TAX 11.24 *** NO CLAIMS WILL BE HONORED UNLESS REPORTED ,r*R TOTAL 156.24 • *** WITHIN 15 DAYS OF THIS INVOICE DATE *** ) 4 Si 03 I n1 g' r "IS CONSL C, r It is agreed between buyer and seller that sale is consummated nd title passed at the plant site The pr of this material has been quoted F.O.B. our plant, and subject to sales tax on material only. Transportation charge for this mate iel is made by Ii need independent tr ck operators at Publi Utilities Commission rates and subject if applicable to transportation tax only. Terms: Net cash. Positively no discount. All accounts due and payable on 10th of month following date of purchase Terms per original Inv ce•inte est will be charged on past due accounts at the highest rate permitted by applicable law. Buyer will pay attorney fees and other collection costs 11_ 4 '. Costa Mesa Sanitary District CONTRACT CHANGE ORDER NO 4 PROJECT #140, #145 Reconstructing Various Sewer Lines TO Miramontes Construction Co , Inc Contractor You are hereby directed to make the herein described changes from the plans and specifications, or do the following work not included in the plans and specifications on the contract. Note: This change order is not effective until approved pursuant to adopted District policy Change Requested by Costa Mesa Sanitary District Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will he made for idle time. During current televising, project, an additional location was discovered necessitating excavation and repair See attached , for location and type of problem Cost to repair negotiated at price similar to existing repairs • Net Increase U Decrease El in Contract $ 1,900. I By reason of this order the time of completi ill be adjusted as follows. pl n4 2 de y t-D G/94/QR Prepared by Robin B Flamers j Date 3/6/98 Approved by Robin B Hamers v Date 3/6/98 Disci ct E g er Approved by District Manager vIctx-t Date 3'9f gel Required whe r as i cost ' $1,000 mor • Board approval also needed when increase in cost exceeds 2% of contract or $1,000 whichever is greater We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment,furnish all materials,except as may otherwise be noted above,and perform all services necessary for the work above specified,and will accept,,ass,,full payment therefor the prices shown above. Data//ccepted 3'I' Contractor Miramontes Construction Co Inc By jL&UllL)- At 1/1∎A' &i? Title Y iOO ? 51 CMF 108E-68 White-District File;Canary-Contr cto Copy.Pink,Fi Golde od-Engi CMSD PROJECT NOS 140 & 145 RECONSTRUCTING VARIOUS SEWER LINES AREA 7 Upstream Downstream MH Distance from Distance from Problem Length of upstream MH downstream MH repair MH 1073-MH 1074 270' 14 OFFSET ± 4 3f0p(Cuj8 1O1s R0. ft.. TQ.CT \� s /K J 19s g 1924 (918 1914 19/2 c 5 O.00 / 73'9 ' P 3 7{-/e M 6 (5/58) /*77 I ' _ '� h 2 , 55(5/•. V .. .7 70 (52 p0 S N +�. • � ti - -wry 1 M �p /I,4U/ h 2gg 1i\\ �o w w / oX 73 (469 (� QC 0 ° w tD \ ' X a m 0 / ti i ti X , r w O e S • kih 6 4 O P/ 23 �P t� 3062 / ,. xpo 9/F/0 44 /925 s c'6, / 3060 /a� 3 51 \ �`���J 1919 19 3058 ie f 3055 <q^' 19�p 15 e "V,4/ 2, /..9 / / 3056 ivy 9 8053 • Sr H 0. i> /0 3 054 3/05 Po 0 Atli) 45 ter' 6x `O'`. 44 20 4*22 \ 3052 � \ I�.�pA9 4 `4(50.94/ I ,. V 3050 201 p 0°'t s .`�' bk /j/ rod /9`9 i� ' CAr L' (1�/99Ci/ 3 4 N 06 I h 3042 2/' m 6_sxi l- / '\ j�:,040 zei%/ 128 G3 N�� ms`s 9/� iON 1 0 h� --I 3038 231 O zs 3tr39 w^I X9/8 /9� 4x • O'Q o� I o 036 zs 30 3037 °� y <9 I 3034 z3 3I 3035 bt" /� Z9 / ij 9 3032 ze 9'' s ,u 3033 Sv' `9� 3030 z �O (X69 ktik%11.*;\ /9/O s �� w'� w a.' o Li 33 3031 `s!9o/en • a w w ° ° y y�0 Z? X�6 � / 0 / N • w o 8 o o w�'' ti & ,• 1 N w tat 9 d /+33 l It '''‘'‘A io Xh 75(5 uDnI: O H. . O/l9 ro a m .. ro • • o / ..V 5 Q J 0 ° '+ O N 2 0 �/ 4 _ 0400 Nm + EST ° ° ° a cliira- A 1 e I. r.cP u o ■ i - Costa Mesa Sanitary District CONTRACT CHANGE ORDER NO 5 • PROJECT #140 #145 Reconstructing Various Sewer Lines TO Miramontes Construction Co Inc Contractor You are hereby directed to make the herein described changes from the plans and specifications, or do the following work not included in the plans and specifications on the contract. Note: This change order is not effective until approved pursuant to adopted District policy Change Requested by Costa Mesa Sanitary District Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. During current televising project an additional location was discovered necessitating excavation and repair See attached for location and type of problem Cost to repair negotiated at price similar to existing repairs Net Increase l_xl Decrease ❑ in Contract $ 1,900. a By reason of this order the time of comp] 01 will be adjusted as follows. plus 2 days to 4/27/98 Prepared by Robin B. Hamers (' I Date 3/6/98 Approved by Robin B. Hamers : Date 3/6/98 District � Approved by District Manager k\L r Date 3/1Ira Requ ed whe i credse cost ' $1,000 mor • Board approval also needed when increase in cost exceeds 2% of contract or $1,000 whichever is greater We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment,furnish all materials,except as may otherwise be noted above,and perform all services necessary for the work above specified,and will accept as full payment therefor the prices shown above. Date accepted 3'ie—qt Contractor Miramontes Construction Co , Inc By 1 -'IL3 O ' Title VI ?1X41 .1r J CMF 1082-68 White-District File Ca ry-contr cto Copy Pink-Fi Golde rod-Engin CMSD PROJECT NOS 140 & 145 RECONSTRUCTING VARIOUS SEWER LINES AREA 7 Upstream Downstream MH Distance from Distance from Problem Length of upstream M-i downstream MI-1 repair MN 1073-MH 1074 142 OFFSET ± 4 1 3!0Q "- 2./..L/8 L., "OUSE R D ,C1) I/P/67- r;V 1 19/8 19/4 92 N.3 57-) / V 1/4i -Z•ilf_64...4 '•-•'/58) ..in•-7,7 .--• - +VI I e ..-' 5.9(St a , 1 sm. '-' 7 to 45-a.0 0, .••• ra ""- -— "I: N. 3 e 5 n• -ni —L___1. I ; . c-•.--- ._ . , ,.. / PI t-, ( . .S\ Ise 23 (4 se ji rh — cq a`? tS cw to G4 t.‘ ...- • IV N 0) °/0 '-7. (ft d ;\*; j• ry , I- -11 D/F-------; % -i _ cn a) 4 a' i 1", t I a pl v, <9,, ; , I • ' "I \ I .. 306 211C‘X \ N0 1 0 2 Lib ca e 11 °C) S.5,>... plo. se \ • 26-, .4060 /51 ,-----'1 obi _..---1, \ c?„, e* c9k, '925 1919 1 Ir 192 0 1915 1 3055 /71 \ ,9 \ I 1( c-1 e /0 t. I 3054 /8 I \----10 / , \ VD \013 ..k- 5 x 0, b , 1 tao "... *N. I 305 2 I \_...- 9 \ C> Aik. 44.2a (:), r_____ - ty i \\II: °4 \ i Cy, \ ---0, -4(5°-921/ bx // Y6 /1,9 i CH..°. <9_3. 3 oi in) - --- _.'t •\<. 1 / —.._ — -4 r---- i 1 c."I <9 er I 128 304 1 _1 I I —_— 30 3e es; 0- 4 x• 293C• 1 oi .0 . /3 I 303 7 i /> n —_ 1so 3 037 17'• 1 cs-, _, ..' I 3034---2-51 1 ' t, 1/r\ 0' 31 3035 ..1) /7 L3 0 32 7:61 76'6.6 1 i ■• 'if, <9,, c3 132 3 033 / %ii .,(6% C't . 1.S0 LAN. 33 303 1 5 'so /,-, 12 r-c; t.4 -4----•1 4 ,,, i/C-5-<'70.2 I C, t_./ .-...„ <3 40 cw t. i, 0" OTh_x <9■-r- c° 0- 0 tl 6)cl g 8 g-/-84 , , cc, -,--,--- ,,, . ! # /co , 1/47,-, •: 11 LI 04 (4.1 -,4 Ciii> — — - 0 I CI 1 pe:S.tsx Lir, • 4, • I - (4 "3" G I., • • ca I 1 /#3.7 111 - 1 I I 3 6> VD- 75(5 xt. "- ?` g(4) .(5, ..., i o '7 ...... CD..t. , ..5% 0 0 p...., '1/4.:" 44 ca .4-‘•"-,Z,c7 • CP n) 020 10 at 1 1 0 P ...., ,5:9 icip, it vb (..2 -- & /- ---- '-----------------o xci3O 0(+uN42KNt-dviNH• ,..:, ..... • "_I ai 78(49.76 tn alii ; WEST c) o i- o,00 ° 1.‘ - 1"--- ca Do 0 0 ------------------------------------.° es * • • CA 0 ro cn _ — • 1 % i cp II• 3?- 1:56:CZ)11 „nallall Costa Mesa Sanitary District CONTRACT CHANGE ORDER NO 6 PROJECT #140 #145 Reconstructing Various Sewer Lines TO Miramontes Construction Co Inc Contractor You are hereby directed to make the herein described changes from the plans and specifications, or do the following work not included in the plans and specifications on the contract. Note: This change order is not effective until approved pursuant to adopted District policy Change Requested by Costa Mesa Sanitary District Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. During current televising project an additional location was discovered necessitating excavation and repair See attached for location and type of problem. Cost to repair negotiated at price similar to existing repairs Net Increase ® Decrease ❑ in Contract $ 1,900 __ By reason of this order the time of completion will be adjusted as follows:Plus 2 days to 4/29/98 Robin B Hamers 3/6/98 Prepared by Date Approved by Robin B Hamer tv Date 3/6/98 Distr ct Engin / Approved by District Manager Date tal`lr Requ ed when " c ea a ost $1,000 mo ' • Board approval also needed when increase in cost exceeds 2% of contract or $1,000 whichever is greater We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment,furnish all materials,except as may otherwise be noted above,and perform all services necessary for the work above specified,and will accept as full payment therefor the prices shown above. Date accepted Contractor Miramontes Construction Co. , Inc. By . �. (4t 4 r Title \66e ?0- -sii>e t CMF 1082-68 White-Distr ct File Canary-Contracto 's Copy Pink-Fi Golde od-Engi CMSD PROJECT NOS 140 & 145 RECONSTRUCTING VARIOUS SEWER LINES AREA 15 Upstream Downstream MH Distance from Distance from Problem Length of upstream MH downstream MH repair MH 149-MH 126 72' 6' hole ± 4 lc SHEET .. .a;_ M + I ,f-I . I 57 03+220N &S I N I �'� I' 0+78. O E r I 1 I 6.0(79.201E &W I. I 60 78.80E 115(73.69)N&S - A • ...as \ 1 19(73.48 N&S 12 VC i w I A 0+64 ()+53 0 c 6 s v 8i :1 2 1, 0+90 I.I0495 ......imp.. CO � � t— w ti�' w N.)0 CI 61 c> a!1 ti3 I+62 N Il71 W co 94 .q OJ CTI (D I IISI N fit 2+21 -4 N 2+32 a N ICI (Q O 2+36 I� 2+35 W U!r OO OD N w Cr 2+72 I O 1 N A 11 �- MIL 2468 0) 01 °'z V. cr C ' 1u ° Jo . 3+23 b Cr: �. ': 615✓ T 1 ltVA 3 4 1; 6 I �(Uj 0 3+47 I� �y 3'46 V WW -a 3+59" �;: Cl) C.71 3+88 '.� 3t90 Q N N Ai 4+04 — �— m M 9.2(81.29) 4+32 �.. P i 4+49 VI — 4+95 mmi y o m - I i rn 5+30 % N (){ i5+39 5+35 of _ I ,� 5Ao . IOZ — 5+61 .,.-A m 8 as — CO` — — 1867 . N : 0(86.05) I W 871 N w m mN-2 ii 1 1855 6+86.00 ; 6+ ..00 AVE . ! 4 W INV. 9 82.43 2+yJ .. � 5.9(82 65)N INV j 4.7(82.57 � S 53-2.'1--4 _ �_._.. I" – – 0�0 6.20 + 1 C + N (0 W + + +44 c+p ++ ) Ao w r y W cn ��' 0+73 SaG n.Z�7 al I+co U1 1+12 1J V� 7+96 1 1+30 +50 ]) 162 8+47 I +84 ' 04- Costa Mesa Sanitary District CONTRACT CHANGE ORDER NO PROJECT #140, #145 Reconstructing Various Sewer Lines TO Miramontes Construction Co. , Inc. Contractor You are hereby directed to make the herein described changes from the plans and specifications, or do the following work not included in the plans and specifications on the contract. Note: This change order is not effective until approved pursuant to adopted District policy Change Requested by Costa Mesa Sanitary District ■ Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. During current televising project, an additional location was discovered necessitating excavation and repair See attached for location and type of problem Cost to repair negotiated at price similar to existing repairs Net Increase © Decrease ❑ in Contract $ 1,900. By reason of this order the time of completion w be adjusted as follows. plus 2 days to 5/1/98 Prepared by Robin B Hamers Date 3/6/98 Approved by Robin B Hamers p L-t Date 3/6/98 Distr'ct Engin �[ Approved•by District Manager NPII! Date 319/4 Requ ed whe In se n cost is $1,000 mo t • Board approval also needed when increase in cost exceeds 2% of contract or $1,000, whichever is greater We, the undersigned Contractor, have given careful conside ation to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials,except as may otherwise be noted above,and perform all services necessary for the work above specified,and will accept as full payment therefor the prices shown above. Date Vt ace- /°,1 Contractor Miramontes Construction Co Inc ( �� v By au& 011�1{r Title 1 1& Pri'eSI vR11/41-1-4 CMF 1082-68 White-District File Ca ry-Contr cto Copy- Pink-Fi Golde od-EngIn CMSD PROJECT NOS 140 & 145 RECONSTRUCTING VARIOUS SEWER LINES AREA 15 Upstream Downstream MH Distance from Distance from Problem Length of upstream MH downstream MH repair MH 1.26-MH 77 8 hole ± 4 a ns f 4 c K+ a �. ri es 3t" t Lra rusaa tom, . mirage? 4 f ,:he DIY I SHEET \ ' j .11HER ST 0+00ESW f„j IS CIT 2:92533 N I 3+20N 9S 1 I 9 8a&S —� �6 OS 73.69))NfiS i -411 lila / 0981 N 18 �. o+53 o o s+ 7. m 1 .p 0+64 0 w r _ �+ I � 0+90 0+95 ��; � N �r e ? `� o I ` -1 - '1 + 1-U1 S 1+62 N ' p I - `' I> 1 N I+71 p v 0 1+90 �' Q) t t\ 1/4)) �, Oda ID I 2+21 w Cy 2+32 . Z I N 2+38 2+35 � r b torn N °w cr 2+ m ' MI 2+95 _� i 3+23 3-21 �f '"4/A 3_4 ►1 __. Wlhi .i Uj 0 3x47 cDla. 1 � �y 3T 46 WW = 4-+ 3+59 � :� J CJ1 "iw. CO S 3+86 I 3t90 Q V A '� IN '�� 92(SL29) 4+32 1111 I 4+� 1 Ut -i -o A' _ r- 4 O 4+95 �. co I — lm 5± o r N 5+39 01.9 ' 5+35 0' ` , 51-61 ma',�' = — 1865 J�°U a$ (fl' ;, 1867 ° 0 rn 85.05) I ' V (-;4 1871 w 0 a 0 J 1- - v 1855 N W W p� J fnNl \I I I\ • 6+ 00 AVE 6*86.009 W INV 9 82.431 2+50 �_...._...-. \ 1 I 5.9(82 65)N INV 4 4.7(829J� f O S �3 2.11 ■ rse a 0 620 V ro ra + + 1 yJJ ) W m D ++ 1 I �a A O. (ii J W 13l 7+46 cn ALA I 0+73 58G 4.Z' cp CP I y 0 +00 U1 1+12 1.. rJ 7-9E +30 5 XS 1+50 (1 I .. 1+62 �- ♦�♦ 8+47 • +6a I N Costa Mesa Sanitary District RECEIVED CONTRACT CHANGE ORDER NO 8 APR 1 7 1998 PROJECT #140. #145 Reconstructing Various Sewer Lines COSTA MESA SANITARY DISTRICT TO Miramontes Construction Co. , Inc. Contractor You are hereby directed to.make the herein desc_nbed changes from the plans'an"d specifications, or do the following work not included in the,plans and specifications on-the contract. Note: This change order is 1101 effective utltil approved pursuant 10 adopted District policy Change Requested by Costa,Mesa „Sanitary-,District., -,_..1 trik.! Description of work to be done, estimate of quantities and prices to be pal • Segregate between additional work at contract price, agieed price an'd`friie iCeiii nt.Unless otherwise'stili , rat for ten erooflequipment cover only such time as equipment•is actually.used-and-no-allowance-wt be made-for-idle-f -----•----1 During the completion of Bid ItemlNo 5c at t manhole. in the I intersection of-19tli S£reet and Anaheim W—, cod£raEEo had to remove an additional. 1 5 vertica';,feot 4:# p-tet'e—encased chimney for each of the manhole drop structures Total additional cost to contractor for both drop structures is $1,496 57 as shown on attached breakdown Acct F+ _ P. T . -- -- --- r .-- F- 4 I I • ' —' t -- — iI L. — -- I t _J Do;.c, .. 1 496.57 Net Increase 14 Decrease ❑ in Contract $ ES By reason of this order the time of completion will be adjusted as follows: None Prepared by Robin B Hamers Date 4/7/98 Approved by Robin B Hamers njaiv Date 4/7/98 Distric Me Approved by District Manager Date Abbe'Required wh 'ncr ase ' cost $1,000 or mor • Board approval also needed when increase in cost exceeds 2% of contract or $1,000 whichever is greater We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment,furnish all materials,except as may otherwise be noted above,and perform all services necessary for the work above specified,and will accept as full payment therefor the prices shown above. Date a'c/epte_d 4/18/98 Contractor Miramontes Construction Co , Inc By Ai r. /U� Title vice President 7 iam Miramontes CMF 1082-68 White-District File Ca ry-Contr cto Copy'Pink-Fin Goide od-Engin _ Costa Mesa Sanitary District R r r 4' E D CONTRACT CHANGE ORDER NO 9 0 5 1998 PROJECT #140, #145 Reconstructing Various Sewer Lines com mEsA SANITARY DISTRICT TO Miramontes Construction Co Contractor You are hereby directed to make the herein described changes from the plans and specifications, or do the following work not included in the plans and specifications on the contract. Note: This change order is not effective until approved pursuant to adopted District policy Change Requested by Costa Mesa Sanitary District . Description of work to be done, estimate of quantities and prices.to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. At Bid Item No 15, Repair #97, Pacific Bell incorrectly marked their line and :then Miramontes was excavating for the sewer repair they damaged the telephone cable. PacBell. came out to the site, removed more of the concrete surface, repaired their line and left Miramontes was delayed in his work plus had to install additional concrete alley apron that was broken out by PacBell. District will. be seeking reimbursement from PacBell. Net Increase © Decrease ❑ in Contract $ 1,854.19 By reason of this order the time of completibn will be adjusted as follows. none Prepared by Robin B flamers ,� Date 4/29/98 Approved by Robin B Hamers 1€ t , Date 4/29/98 District Engine Is , Approved by District Manager !iii►' Date Rego' ed whe • se i st ' $1;000 no • Board approval also needed when increase in cost exceeds 2% of contract or $1,000 whichever is greater We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved. that we will provide all equipment,furnish all materials,except as may otherwise be noted above,and perform all services necessary for the work abov specified,and will accept as full payment therefor the prices shown above. May 1 1998 Miramontes Construction Co. , Inc. Date ac epted 1� Contractor By IJ L4 1�� 'Title Vice President riam Miramontes CMF 1082-68 White-Distr ct File Ca ry-Contr ctor Copy'Pink-Fin Golde rtl-Engi i , W a= i �� ! � � H . � iil ' Oj •—a' I I 1 011 1 y` I { 1 --I' �,• .. Z I I I co I .-I W Q '4 C. 1 F a O_, O a > 1 ,,-JI o F a) ° I:I I ism I J. ii I < m I < m F z LI gr S C " a Zc CY I IM F -I M I a < 1 F m❑ a o ,pi a O O a to AI a O• Z v a 0 O U U I 1 z y < < V < E-0 G ¢ • Q < 3 0 14 Id S F ] x n m } G G S F 1 2 V u u ) u U a IIi a YC F ¢ ¢ C F C U •-_,1 V »G U U C OI O� 0 HO 0 C u , 1 O U G _ -o :0 F < 9 a G a o F K O ■ C z y la JL C7 y I _ Z Z Q Al = m a+W F ?; Vl I J. j 0 G a i .0 1 °,� < Q m G W � .a L-. I W 0 •• 0 0 H ~ J i N O . a r In N a' - _, I s. a Y Y III • c l I .,{ U p W _ i re, u• r n I 14 o y U l NM IS •1 Y i.• CI I •• W a Ch 2 rrrrrirrrrrrrrrr a• ' : a W P . ; : i - =r =rrrrrrrriri r_P o } ^ = rrrrriiiiiri 11�; lll�.IC CO N ] CC 0 C y I t�rr 1 N U 1il X .0 0 b J Inn' rrrrrrrri� liii CI u0N _ 11 =2 L to C b < ta O Cr O C.. 0 LO VD < 6 O W T 2 0 iJ Z IQ 'J , 0 :4 Z _, 3 p CI� I I • I C :4 W -, II IW ca < yy W. O .H C N F 0 0 1 a m 6. 3 < r1 ` .( -' = co 1+ II y u O N Z I W O i+ Z 1 , W I i� O > $ i ,. 3 I o 1 a W. d r 4. O E m < U = d y F m G 'O v) Y 1"' a iii I v 4: a 1 W .a Y >a I O , a W. C C W I� U m N. U r' A. z 6 • w S p v .3 --�. 3 FOi G I • a 2'ir. }- W P -.Y 0 0 Y. p N a) p v F C ( 0. 1 a F al a. •F. • y a E G o U 4 a O r o O I• y I I W .: Z a m !Oi J -� ti a G1 V U I . I °