Loading...
15 - CIP Updates September 2014 Board Meeting COSTA MESA SANITARY DISTRICT CAPITAL IMPROVEMENT PROGRAM FY2013-2014 PROJECT:PROJECT MANAGER:DESCRIPTION:BEGIN DESIGN:CONSTRUCTION COMPLETION DATE: Preliminary Civil Engineering - $131,047; Estimated construction cost - $3.77 million 9/3/14 - Additional Preliminary Engineering Allocation - $10,000 STATUS REPORT:12/20/10 - No change.01/27/11 - No change.5/26/11 - Staff met with another potential OCSD consultant to review OCSD's scope of work. OCSD will soon be publishing their RFP.10/27/11 - OCSD selected Dudley as its consultant and is finalizing the consultant contract.11/30/11 - No change.10/26/10 - OCSD requested copies of all CMSD pumping station plans, which were provided. OCSD anticipates hiring a consultant to prepare an EIR and alignment study in 2011. CMSD requested a joint EIR.9/23/10 - OCSD was provided with plans, maps and flow figures for their review. OCSD will be hiring a consultant to prepare the design for their facilities. 4/28/11 - Staff met with 3 proposed OCSD consultants to explain the project. OCSD's first phase of work will be an EIR and alignment study and the CMSD requested the OCSD EIR cover the CMSD work. 03/24/11 - Staff met with OCSD Project Managers on 3/8/11 to review OCSD's scope of work and project timing.8/26/10 CMSD staff and two Directors met with OCSD staff on 8/4/10 to discuss the framework of the project. OCSD will be constructing its own gravity sewer to accept the CMSD and CNB flows and send it under the Santa Ana River to OCSD Plant No. 2. OCSD Abandon 6 CMSD pumping stations, abandon the CNB station in the CNB island on W. 19th Street, and abandon the private pumping station on W. 18th Street by constructing new gravity lines. The project would also alleviate the north half of the Banning Ranch. A preliminary engineer's estimate is $3 million.#101 West Side Pumping Station Abandonment 7/1/2012 3/25/2019 Rob Hamers, District Engineer 12/15/11 - OCSD staff attended CMSD SSC meeting on 11/8/11 to discuss project timeline.1/26/12 - Kickoff meeting for OCSD's consultant Dudek scheduled for 1/11/12. Consultant has placed flow meters in CMSD lines to confirm flows.11/18/10 - No change.9/22/11 - OCSD is evaluating consultant proposals.8/25/11 - No change.02/24/11 - No change. Staff will be contacting OCSD to review their status. 7/28/11 - OCSD's preliminary schedule reflects completion of construction of OCSD's sewer facilities on 3/25/2019.6/23/11 - No change.ITEM NO. 15 COSTA MESA SANITARY DISTRICT CAPITAL IMPROVEMENT PROGRAM FY2013-2014 PROJECT:#101 West Side Pumping Station Abandonment 8/20/12 - OCSD's surveyors are working on the topogaphy.3/28/13 - The District Engineer provided a narrative and map explaining the District's work to be included in the EIR NOP.5/23/13 - Engineer's Estimates for the work are being prepared.6/27/13 - Engineer's Estimates for the work are being prepared; the District Engineer reviewed 2 sections of the OCSD EIR as requested.8/29/13 - The Board will review the District Engineer's staff report on the preliminary engineering at the 8/20/13 study session.9/26/13 - The Preliminary Engineering report will be reviewed at the October 15 Study Session.10/24/13 - The Preliminary Engineering Report will be reviewed at the October 15 Study Session.11/21/13 - The preliminary engineering report was reviewed at the 11/12/13 study session.12/19/13 - No change in status.1/23/14 - No change in status.2/25/14 - No change in status.3/27/14 -No change in status.4/24/14 - No change in status.5/22/14 - No change in staus.6/26/14 - The EIR is complete and will go to the OCSD Board for certification on 7/23/14. The OCSD RFP for final design will be advertised in August.7/24/14 - A special meeting is set for 7/22/14 to determine funding for potentially high park restoration and maintenance costs.9/25/14 -OCSD certified the project EIR; CMSD is completing a limited soils investigation to determine microtunneling costs and total project costs.Account Number Encumbrances Balance #101 2,541,625 $ 172,724 $ 1,126 $ 5,000 $ 2,362,774 $ 7/25/13 - The District Engineer will be providing the preliminary budget at the 7/25/13 regular meeting.11/15/12 - The District Engineer is continuing working with the topography provided by OCSD's surveyors.10/25/12 - The District Engineer is continuing working with the topography provided by OCSD's surveyors.6/28/12 - District Engineer is working with OCSD consultant on confluence point for CMSD/CNB/OCSD sewers.7/26/12 - CMSD will be obtaining topographic informatin from OCSD's consultant and will sve $4,500 in the process due to cost sharing.4/18/13 - The District Engineer is continuing work on the preliminary engineering.9/20/12 - The District Engineer has begun working with the topography provided by OCSD's surveyors and aerial photogrammist.2/28/13 - The District Engineer is continuing work on the preliminary engineering. Approved Proj Budget June 30, 2014 Accumulated Cost Current Year Expenditures 2/23/12 - CMSD District Engineer is providing scope of work for preliminary engineering for Board consideration.3/22/12 - CMSD District Engineer is providing preliminary engineering fee for Board consideration.5/24/12 - The Board approved the District's Engineer's proposal for the Preliminary Engineering.4/16/12 - The Board is considering the District Engineer's proposal to perform the Prelimanary Engineering.8/28/14 - CMSD and OCSD are preparing Engineer's Estimates for CMSD's portion of the work. OCSD has proposed an Agreement on the need for all abandonment facilities to be in operation.1/24/13 - The District Engineer is continuing work on the preliminary engineering.12/20/12 - The District Engineer is continuing work on the preliminary engineering. COSTA MESA SANITARY DISTRICT CAPITAL IMPROVEMENT PROGRAM FY2013-2014 PROJECT:#101 West Side Pumping Station Abandonment Total 2,541,625 $ 172,724 $ 1,126 $ 5,000 $ 2,362,774 $ COSTA MESA SANITARY DISTRICT CAPITAL IMPROVEMENT PROGRAM FY2013-2014 PROJECT:PROJECT MANAGER:DESCRIPTION:BEGIN DESIGN:APPROX. CONSTRUCTION COMPLETION DATE:Civil Design - $21,133.50; Civil Contract/Admin/Inspection - $48,470 #196-A (Victoria, Mendoza & Elden By-Pass Pumps) - Engineer's Estimate: $500,000 #196-B (Canyon Generator) - Engineer's Estimate: $100,000 STATUS REPORT:3/28/13 - The District Engineer and General Manager are working with the cities of Costa Mesa and Newport Beach regarding above-ground emergency equipment.4/18/13 - No change in status.5/23/13 - A soils investigation is being performed for the 23rd P.S. location in the right-of-way slope. Two other locations will be housed in prefabricated buildings.6/27/13 - The City of Costa Mesa is reviewing the design for the 3 stations in Costa Mesa 9/26/13 - The District Engineer has provided a staff report for the 9/26/13 regular meeting on the status of the project.10/24/13 - Installation at the Elden, Victoria, and Mendoza stations is out to bid as 196-A, and installation at the Canyon Station is out to bid as 196-B.11/21/13 - Bid opening for 196-B Canyon Generator was 11/5/13 and the low bidder is Avram Electric in the amount of $64,815.12/19/13 - Bid opening for 196-A was held 11/20/13 and award of the construction contract is on the 12/19/13 agenda to GCI in the amount of $485,200 and the equipment is another $222,080.1/23/14 - Work is occurring on 196-A at Elden, Victoria, and Mendoza pump stations and #196-B at Canyon pump station.2/25/14 - Construction on #196-A is 10% complete and #196-B is 50% complete.3/27/14 - Construction on #196-A is 15% complete and #196-B is 60% complete.4/24/14 - #196-A is 40% complete and #196-B is 95% complete.5/22/14 - The building was installed at Victoria PS on 5/8/14; #196-A is 75% complete. #196-B is complete.6/26/14 - Installation of the backup pumping units at Victoria and Mendoza pump stations is complete.7/24/14 - Installation at Elden will continue after contractor moves golf course fence.8/28/14 - The District/SACC Agreement for moving the golf course fence was approved and construction is set to continue.9/25/14 - #196-A Elden, Victoria, Mendoza back-up pumps is now complete; #196-B Generator at Canyon pump station is complete; #196-C 23rd back-up pump is in design at structuralo engineer; #196-D Generator at Irvine pump station; waiting on Gas Co. for proposed meter location prior to finalizing plans.Account Number Encumbrances Balance #196-A Elden, Victoria, Mendoza Pump Stations 790,000 $ 572,977 $ 3,060 $ 178,515 $ 35,448 $ #196-B Canyon Pump Station 140,000 115,335 - - 24,665 #196-C 23rd Street Pump Station 65,000 14,546 - - 50,454 #196-D Irvine Pump Station 65,000 89,462 38,894 - (63,355) Total 1,060,000 $ 792,320 $ 41,954 $ 178,515 $ 47,212 $ #196 Installation of Backup Power and Pumping Capability Rob Hamers, District Engineer Install backup standby diesel generator at two pumping stations and install backup pumping systems at April 23, 2012 05/24/12 - District's Engineer's office is in design of the backup pumping systems while another consultant, PDE, is in design on the standby diesel generators.June 30, 2014 Accumulated Cost Current Year Expenditures 10/25/12 - The District Engineer is working with the cities of Costa Mesa and Newport Beach regarding above-ground emergency equipment.01/24/13 - The District Engineer and General Manager are working with the cities of Costa Mesa and Newport Beach regarding above-ground emergency 12/20/12 - The District Engineer and General Manager are working with the cities of Costa Mesa and Newport Beach regarding above-ground emergency 8/29/13 - The District Engineer is finalizing the plans for the backup pumping units at Elden, Victoria, and Mendoza. The District Engineer is also finalizing the plans for the 9/20/12 - Plans were submitted to the cities of Costa Mesa and Newport Beach for first plan check.7/25/13 - Engineering staff is awaiting City of Costa Mesa comments on building design at three sites, while 23rd station in Newport Beach is in design.Jan - 15 6/28/12 - Plans and specs are 30% complete.11/15/12 - The District Engineer is working with the cities of Costa Mesa and Newport Beach regarding above-ground emergency equipment.02/27/13 - The District Engineer and General Manager are working with the cities of Costa Mesa and Newport Beach regarding above-ground emergency 7/26/12 - Plans and specs are 60% complete.8/20/12 - Engineering staff is performing final review prior to submitting the plans for plan check. Approved Project Budget COSTA MESA SANITARY DISTRICT CAPITAL IMPROVEMENT PROGRAM FY2013-2014 PROJECT:PROJECT MANAGER:DESCRIPTION:BEGIN DESIGN:APPROX. CONSTRUCTION COMPLETION DATE:Civil Design: $58,739; Civil Contract Admin/Inspection - $17,269; Construction Engineer's Estimate: $318,000 STATUS REPORT:11/15/12 - The design phase is continuing.3/28/13 - The plans and specifications will be submitted for first plan check by the end of March 2013.4/18/13 - The plans were submitted to Costa Mesa and Newport Beach for 1st review on 4/1/13.5/23/13 - The project went out to bid on May 3, 2013 and bid opening is June 4, 2013.6/27/13 - Bid opening was 6/4/13 and the low bidder is Charles King Co., the same contractor as Phase II, in the amount of $228,700.8/29/13 - The first day of work was 7/26/13.9/26/13 - Work is approximately 75% complete on installation of liners and dig and replace repairs.10/24/13 - Work was re-started after a shortage of lining material occurred.11/21/13 - Work is continuing and is 80% complete.12/19/13 - All work is complete except for the extra work of full length lining in two, and possibly three, areas.1/23/14 - No work occurred from Thanksgiving to New Years due to City holiday closure so the remaining work (which is extra work) can be completed.2/25/14 - The contractor is obtaining additional estimates for the extra work. The regular work is complete.3/27/14 - The extra work will be moved to a separate project. The Board will finalize the project at the March 2014 regular meeting.4/24/14 - The project #197A is complete.4/24/14 - P roject 197B engineering for additional Grade 5 discovered and Hotspots is complete. Project is out to bid.5/22/14 - 197-B being awarded to Sancon for $111,000. Engineer's estimate is $114,600.6/26/14 - The construction contract for 197-B is fully executed and the contractor is acquiring materials.7/24/14 - Contractor will begin work on Project #197-B in late July.8/28/14 - Work began on #197-B on 7/28/14 and will end on 8/14 /14. Board will final project on 8/28/14.9/25/14 - Project is complete.June 30, 2014 Account Number Accumulated Cost Encumbrances Balance #197A 300,000 $ 306,608 $ -$ -$ (6,608)$ #197B 370,000 11,573 1,068 111,000 246,360 Total 670,000 $ 318,181 $ 1,068 $ 111,000 $ 239,752 $ #197 System Wide Sewer Reconstruction Phase III Rob Hamers, District Engineer Sep-12 Nov-13 01/24/12 - The plans and specs are approximately 50% complete.Phase 3 of Grade 5 repairs. Grade 5s are pipe problems ready for failure that were found during the 2006-2009 District-wide televising project. There are approximately 69 pipe segments with one or more Grade 5s that will be 12/20/12 - The design is continuing.7/25/13 - The pre-construction meeting is 7/11/13 and construction is tentatively scheduled to begin in late July. Approved Proj Budget Current Year Expenditures 10/25/12 - The design phase is underway.02/27/13 - The plans and specs are approximately 75% complete. COSTA MESA SANITARY DISTRICT CAPITAL IMPROVEMENT PROGRAM FY2013-2014 PROJECT:PROJECT MANAGER:DESCRIPTION:BEGIN DESIGN:APPROX. CONSTRUCTION COMPLETION DATE:Civil Design - $82,593 STATUS REPORT:1/23/14 - The design phase is continuing.5/22/14 -Mendoza force main is out to bid as a separate project due to upcoming City alley project. Engineer's estimate is $102,000. Bid opening is 6/2/14.6/26/14 - GCI Construction is low bidder in the amount of $82,540 for Project #200-A Mendoza Force Main.7/24/14 - 1st day of work for Project #200-A was 6/23/14; plans are 75% complete for Harbor, Victoria, SCP.8/28/14 - All work w a s completed on #200-A Mendoza force main and the Board will final the project on 8/28/14.9/25/14 - #200-A Mendoza pump station new force main is complete. Design phase of Harbor, Victoria & South Coast Plaza continuing; will be meeting with South Coast Plaza.Account Number Encumbrances Balance #200 1,030,868 $ 109,847 $ 40,976 $ 26,395 $ 853,650 $ Total 1,030,868 $ 109,847 $ 40,976 $ 26,395 $ 853,650 $ #200 Rehabilitation of Four Force Mains Rob Hamers, District Engineer The Wilson, Victoria, Mendoza, and South Coast Plaza force mains are being replaced with new force mains.Dec-13 Late 2014 12/19/13 The design phase has begun.2/25/14 - The design phase is 40% complete.3/27/14 - The design phse is 60% complete.4/24/14 - The design phase is 70% complete. Approved Proj Budget June 30, 2014 Accumulated Current Year Expenditures COSTA MESA SANITARY DISTRICT CAPITAL IMPROVEMENT PROGRAM FY2013-2014 PROJECT:PROJECT MANAGER:DESCRIPTION:BEGIN DESIGN:APPROX. CONSTRUCTION COMPLETION DATE:Estimated Project budget: Civil Design $11,483.50; Construction - Engineer's Estimate : $431,210 STATUS REPORT:12/19/13 - The plans are 90% complete and the Engineer's Estimate is being prepared.2/25/14 - The project is being discussed at the study session.5/22/14 - The strategic improvements for this project were constructed on 5/8/14.6/26/14 - No change in status.7/24/14 - The remaining improvements under this project will likely be constructed in the 2015-16 fiscal year.8/28/14 - The project will likely receive funding in the 2015-20 16 Fiscal Year to complete the replacement.9/25/14 - No change in status.Accumulated Current Year Approved Cost to Date Account Number Project Budget As of 6/30/2014 Expenditures Encumbrances Balance #202 150,000 $ 10,567 $ -$ -$ 139,433 $ Total 150,000 $ 10,567 $ -$ -$ 139,433 $ December, 2014 #202 Elden Piping and Valve Replacement Rob Hamers, District Engineer Replace 37-year old piping and valves outside Elden Pumping Station; includes valves and piping on Elden force main and remaining section of Irvine force main.October, 2013 3/27/14 - The need for additional funding has moved the project into the next 2-year budget cycle, beginning 2015-2016; strategic improvements are being included as extra work in Project #196-A.1/23/14 - The plans are 100% complete. Staff is exploring combining this work with 196-A, installation of a backup pump at Elden Pump Station.10/24/13 - Engineering staff met with the field crew to discuss possible additional replacement of valves inside station.11/21/13 - The design phase is continuing; the plans are 60% complete.4/24/14 - The strategic improvements for this project were added to Project #196-A. COSTA MESA SANITARY DISTRICT CAPITAL IMPROVEMENT PROGRAM FY2013-2014 PROJECT:PROJECT MANAGER:DESCRIPTION:BEGIN DESIGN:October 2013 APPROX. CONSTRUCTION COMPLETION DATE:June 2014 Architectural Design - $7,000; Electrical Engineering Design - $4,500 STATUS REPORT: 10/3/2013 - Entered into agreement with RTA Architects to design and provide construction administration services 11/7/2013 - Reviewed SCE 12 months bills at the Yard to determine load demand and size of the generator 12/1/2013 - Project manager meeting. Possible generator manufacturers are Caterpillar, Cummins and Kohler.1/23/14 - No change in status.2/25/14 -RFP for design firms is being prepared.3/27/14 - Proposals are being requested from design firms for the design phase.4/24/14 - An electrical engineer has been retained for the design phase for a fee of $4,500.5/22/14 - The plans were submitted to the City of Costa Mesa for 1st plan review.6/26/14 - The design plans are in plan check and being re-submitted to the City.7/24/14 - Plans were resubmitted to the fire department for 2nd review; all other departments have signed off.8/28/14 - The project is out to bid.9/25/14 - Bid opening is being handled by the CMSD GM and project architect.Accumulated Cost Account Number June 30, 2014 Encumbrances Balance #203 150,000 $ 5,462 $ 1,312 $ 9,038 $ 134,188 $ Total 150,000 $ 5,462 $ 1,312 $ 9,038 $ 134,188 $ Approved Project Budget Current Year Expenditures #203 Emergency Generator at District Yard Scott Carroll, General Manager Procure and install an emergency generator at the District Yard COSTA MESA SANITARY DISTRICT CAPITAL IMPROVEMENT PROGRAM FY2013-2014 PROJECT:PROJECT MANAGER:DESCRIPTION:BEGIN DESIGN:APPROX. CONSTRUCTION COMPLETION DATE:Civil Design - $9,779 STATUS REPORT:6/26/14 - The plans are 60% complete.7/24/14 - The project went out to bid on 7/2/14 with bid opening scheduled for 8/5/14.8/28/14 - Bid opening was 8/5/14 and the low bid was Excel Paving in the amount of $87,349.00.9/25/14 - Notice to proceed issued to Excel Paving to begin work 9/15/14; Field Crew requesting additional manholes be added as extra work.June 30,2014 Account Number Encumbrances Balance #204 100,000 $ 9,119 $ -$ 87,349 $ 3,532 $ Total 100,000 $ 9,119 $ -$ 87,349 $ 3,532 $ Approved Proj Budget June 30, 2013 Accumulated Current Year Expenditures 4/24/14 - The design phase is in process #204 Manhole Cover Repairs Rob Hamers, District Engineer Repair 102 manhole covers Feb-14 Late 2014 2/25/14 Project approved by Board, fund appropriated.5/22/14 - The plans are 40% complete. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 25 26 27 28 29 30 31 32 33 34 35 36 37 A B C D E F G H I J K L M PROJECT:PROJECT MANAGER:DESCRIPTION: BEGIN DESIGN:APPROX. CONSTRUCTION COMPLETION DATE:Civil Design -STATUS REPORT:9/25/14 - Engineering staff reviewing CCTV for Grade 4s in streets set for City improvements such as new paving or slurry seal. One Grade 5 found in Canadian; Mike Kilbride Ltd. will excavate and repair.June 30, 2014 Account Number Encumbrances Balance #306 568,000 $ 2,557 $ -$ -$ 565,443 $ 568,000 $ 2,557 $ -$ -$ 565,443 $ #206 Grade 4 Repairs - Phase I Rob Hamers, District Engineer Aug-14 Jun-15 District has 1,600 line sections with one or more Grade 4 deficiencies. Approximately 75 line sections will be repaired in Phase I. Approved Proj Budget June 30, 2013 Accumulated Current Year Expenditures 8/28/14 - The design phase is underway.