Memorandum
To: Board of Directors
Via: Scott Carroll, General Manager
From: Rob Hamers, District Engineer
Date: October 24, 2013
Subject: Grant of Easement to Costa Mesa Sanitary District for a Standby Diesel
Generator at Canyon Lift Station – Project #196-B
Summary
The goal of Project #196 is to provide backup power and backup pumping capability at six
critical lift stations. The Irvine and Canyon pumping stations will have standby diesel
generators and the Elden, Victoria, Mendoza and 23 rd pumping stations will have backup
pumping units. An easement for the generator and conduit is needed from two private
property owners at the Canyon lift station, and enclosed for Board consideration is the
proposed agreement with these two property owners.
Staff Recommendation
The Board of Directors approves and executes the easement agreement.
Analysis
District staff is challenged with the new reality that Southern California Edison power is not
as reliable as in years past. This project will provide a standby diesel generator at the
Canyon lift station until such time as the station is abandoned as part of the west side
abandonment project. At that time, the generator will be relocated to another pumping
station.
ITEM NO. 18
Board of Directors
October 24 , 2013
Page 2 of 3
The attached agreement represents successful negotiations with the two property owners
where the generator and conduits will be constructed. The compensation for the 5 -year
period of the agreement is a one -time payment of $5,000 to the owner of 2247 State
Avenu e and a one -time payment of $3,1 00 to the owner of 2250 Canyon Drive. Should
delays in the abandonment project occur, the District an d the property owners will
negotiate the extension in good faith.
The construction plans for the new generator were placed out to bid on October 9, 2013
and bid opening is scheduled for November 5, 2013.
Strategic Plan Element & Goal
This item complies wi th the objective and strategy of Strategic Plan Element 1.0, Sewer
Infrastructure , which states as follows :
”Objective: Our objective is to collect and transport wastewater to meet the needs of
existing and future customers.
Strategy: We will do this by the careful management of the collection infrastructure using
prudent planning and maintenance, with financial strategies to maintain sufficient capacity
and respond to changing regulatory demands.”
Legal Review
This easement agreement was prepared and s igned by the Associate District Counsel.
Environmental Review
The installation of a backup generator is categorically exempt under the California
Environmental Quality Act (CEQA) (Public Resources Code Section 21000 et. s eq.) under
Section 15301 as a “Class 1” “minor alteration of existing public or private structures”, as
further described in S ection (b) as “Existing facilities of both investor and publicly -owned
utilities used to provide …. sewerage …”
Financial Review
The total cost to compensate t he two property owners is $8,100 . The cost associated with
this lease agreement will be included in the overall project cost, which has a current
balance of $995,388 .
Public Notice Process
Copies of this report are on file and will be included with the e ntire agenda packet for the
October 24 , 2013 regular Board of Directors meeting at District Headquarters and on the
District website.
Board of Directors
October 24 , 2013
Page 3 of 3
Alternative Actions
1. Direct staff to report back with more information.
Attachment A: Ea sement Agreement
Reviewed by:
Stacey Cuevas
Finance Manager