Memorandum
T o: Board of Directors
Via: Scott Carroll, General Manager
From: Elizabeth Pham, Management Assistant
Date: October 15, 2013
Subject: Sewer Lateral Assistance Program (SLAP) – Fiscal Year 2008 -2013 Analysis
Summary
The Costa Mesa Sanitary District (CMSD) Board adopted its Sewer Lateral Assistance
Program (SLAP) as a financial incentive program to encourage residents to maintain
their l ateral sewer lines. Staff is providing the Board of Directors with a 5 -year analysis
on the scope of services that have been rendered during this period.
Staff Recommendation
Staff recommends t hat the Board of Directors receive and file this report.
Analysis
Without regular maintenance sewer lines can become blocked and cause material to
back up into the house and the environment. The District reimburses 50% of the
resident’s cost up to a maximum of $1,600 per residential parce l for services that may
include televising the lateral interior, cleaning the pipe, installing a clean out
attachment, and reconstruction costs.
The following graphs illustrate the services that have been reimbursed within the last
five years:
Board of Directors Study Session
October 15 , 201 3
Page 2 of 5
The following servi ces were performed during Fiscal Year 2008 -2009:
124 participants televised their lateral.
8 3 participants had cleaning services.
70 participants had a clean out installed .
48 participants had root cutting work.
33 participants had their lining rehabilitat ed.
2 2 participants had spot repair work.
23 participants had new laterals installed.
The following services were performed during Fiscal Year 2009 -2010:
111 participants televised their lateral.
74 participants had cleaning services.
91 participants h ad a clean out installed .
47 participants had root cutting work.
33 participants had their lining rehabilitated.
Board of Directors Study Session
October 15 , 201 3
Page 3 of 5
15 participants had spot repair work.
16 participants had new laterals installed.
5 participants had cured in place pipe work.
The followi ng services were performed during Fiscal Year 2010 -2011:
124 participants televised their lateral.
80 participants had cleaning services.
93 participants had a clean out installed .
50 participants had root cutting work.
28 participants had spot repair work .
12 participants had new laterals installed.
28 participants had cured in place pipe work.
The following services were performed during Fiscal Year 2011 -2012:
Board of Directors Study Session
October 15 , 201 3
Page 4 of 5
136 participants televised their lateral.
64 participants had cleaning services.
95 particip ants had a clean out installed .
28 participants had root cutting work.
1 participant had their lining rehabilitated.
36 participants had spot repair work.
10 participants had new laterals installed.
44 participants had cured in place pipe work.
The fol lowing services were performed during Fiscal Year 201 2 -201 3 :
156 participants televised their lateral.
53 participants had cleaning services.
118 participants had a clean out installed .
12 participants had root cutting work.
28 participants had spot repair work.
5 participants had new laterals installed.
10 participants had cured in place pipe work.
Strategic Plan Element & Goal
This item adheres to Strategic Element 1.0, Sewer Infrastructure, and Strategic Goal
No. 1.9, Sewer Lateral Assistance Program.
Legal Review
Not applicable at this time.
Board of Directors Study Session
October 15 , 201 3
Page 5 of 5
Environmental Review
The payment by the District of funds to assist residents in the repair and rehabilitation
of their private laterals does not meet the definition of a project under CEQA or
CMSD’s C EQA Guidelines.
Financial Review
For the current Fiscal Year, staff has allocated $200,000 as the program budget. Staff
will continue to monitor this program and inform the Board if additional funds are
needed.
Public Notice Process
Copies of this re port are on file and will be included with the complete agenda packet
for the October 15, 2013 Board of Directors Study Session meeting at District
Headquarters and posted on the District’s website .