Project 123 - Change Order #1 - Schuler Engineering - 1992-01-30 Costa Mesa Sanitary District
CONTRACT CHANGE ORDER NO 1
t'
PROJECT 1112100-123 Pump Station Recoating and Maintenance •
TO Schuler Engineering Corp Contractor
You are hereby directed to make the herein described changes from the plans and specifications, or do the
following work not included in the plans and specifications on the contract.
Note: This change order is not effective until approved pursuant to adopted District policy
Change Requested by Costa Mesa Sanitary District
9
Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work
at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only
such time as equipment is actually used and no allowance will be made for idle time.
Bid Item 4 calls for removing the deteriorated electrical junction
boxes in Tustin and Mendoza Pumping Stations and then sealing the
conduits to prevent gas from entering the conduits and then entering
the electrical enclosure However, due to the power cable arrangement
within the conduits there is no way to seal the conduits without a
new electrical junction box Therefore, 1 new .electrical junction
box is needed for each station The total cost for labor and
materials for both boxes is $1,475 00 as shown on the attached
letter from Schuler Engineering
Net Increase VA Decrease ❑ in Contract $ 1,475.00
4
By reason of this order the time of completion will be adjusted as follows. None
Prepared by Robin B. Homers Date 1/30/92
Approved by B.
Auk Date I/30 kb'
Piz • t Engine nr ^ ��
Approved by District Manager l Y�U^ Date 71 3/q Z
Requi end whe 'n r In st Is $1,000 mor
• Board approval also needed wizen increase in cost exceeds 2% of contract or $1,000 whichever is greater
We, the undersigned Contractor have given careful consideration to the change proposed and hereby agree, if this proposal is approved,
that we will provide all equipment,furnish all materials,except as may otherwise be noted above,and perform all services necessary for the
work above specified,and will accept as full payment therefor the prices shown above.
Date accepter 7 /?2— Contractor Schuler Engineering Inc.
By � Title President
-3raucc 6cHvwR-
CMF 1082-68 White-Distr ct File Ca ry-Contr cto Copy' Pink-Fi Caine od-Engin
chuler
engineering corp.
January 30, 1992
Costa Mesa Sanitary District
234 E. 17th Street
Costa Mesa, Calif. 92627
Attention: Mr Rob Hammers
Reference: Contract # 1112100-123
Subject: Change in Electrical Items
Gentlemen,
The change requested for junction boxes in the Tustin Station wet
well may be completed for a lump sum price of $1475 The sizes are
per your instruction to West Electric and they will be submersion
proof
Very ' Yours,
4
Bruce A. Schuler
President