Project 125 - Proposal - Hamers - 1992-03-26 5) ROBIN B. HAMERS
234 E 17TH ST SUITE 205
& ASSOCIATES, INC. COSTA MESA,CA 92627
CIVIL ENGINEERS PLANNERS SURVEYORS (714J540-1192
March 26 1992
Board of Directors
Costa Mesa Sanitary District
P 0 Box 1200
Costa Mesa CA 92628
RE PROPOSAL TO COMPLETE CONSTRUCTION PHASE
PROJECT 1112100-125 TELEVISING SEWER LINES
Gentlemen
The following proposal is submitted to provide the necessary
engineering services during the construction phase of said
project
Construction is scheduled to be completed within a 6 month period
beginning in June The necessary services to oversee the project
are engineering drafting and inspection and the estimated
maximum number of hours and proposed rate for each are as
follows
Engineering 80 hrs @ $ 55 00/hr = $ 4 400 00
Drafting 6 hrs @ $ 44 00/hr 264 00
Inspection 600 hrs @ $ 39 00/hr 23 400 00
TOTAL $ 28 064 00
The above are maximums and billing will be only for actual time
worked
Sincerely,
WJAA,
Robin B Hamers
RBH/jp/proposal cms
fa Printed on Recycled Paper.