CONTRACT CHANGE ORDER NO 1
PROJECT 1112100-126 Reconstructing Various Sewer Lines
TO Grgo & Gordon Grbavac Construction Co Inc Contractor
You are hereby directed to make the herein described changes from the plans and specifications, or do the
following work not included in the plans and specifications on the contract.
Note: This change order is not effective until approved pursuant to adopted District policy
Change Requested by Costa Mesa Sanitary District
4
Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work
at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only
such time as equipment is actually used and no allowance will be made for idle time.
The anticipated amount of pipe replacement for each individual spot
repair was based on reviewing the TV video taken from inside the line
In some cases the amount of damaged pipe seen from inside the line does
not reflect the total damage as seen after the line is uncovered For
instance a hole in the pipe seen from the inside may be in reality just
part of a lengthy section of cracked pipe, the cracks not having yet pene-
trated to the inside of the pipe to become visible during the TV inspectic
Therefore the contractor must replace the entire damaged section Also
during some excavations unanticipated obstructions are present such as
other utilities or concrete The amount of extra work on each location
was negotiated to reflect the actual circumstances. See attached infor-
mation for a detailed description of each location and the extra work
required
Net Increase ® Decrease O in Contract $ -13,400.00
it
By reason of this order the time of completion will be adjusted as follows: None
Prepared by Robin B H mers Date 1/27/94
Approved by Date 1/27/94
Dls ct Engi eer
I
Approved by District Manager �^o'''', Date 1/27/94
Require eh n "ncrease ' cost is $1,000 mo
• Board approval also needed when increase in cost exceeds 2% of contract or $1,000 whichever is greater
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved,
that we will provide e., pment, furnish all materials,except as may otherwise be noted above,and perform all services necessary for the
work above specif .• €will accept as full payment therefor the prices shown above.
Date acc/ 1/28/94 Contractor Grgo & Gordon Grbavac Construction Co In
By 1" ' — Title President
CMF 1082-68 White-Distr ct File Ca ry-Contr cta Copy-Pink-Fin Goltle od-Engin
PROJECT 1112100-126 RECONSTRUCTING VARIOUS SEWER LINES
Change Order No 1 January 27 1994
Bid Item Description of Work Extra Work Amount
1 Bid Item 5 Instead of replacing 4' of pipe $3 250 00
Line #21 contractor replaced 9 and had to remove
existing concrete encasement Had to
work around exist telephone duct
2 Bid Item 7 Deleted from project. Was repaired (2 600 00)
Line #30 using Link-Pipe
3 Bid Item 9 Installed 4 1/2 of pipe instead of 3 650 00
Line #43 Extra hand digging
4 Bid Item 11 Instead of replacing 4 of pipe and 1 1 950 00
Line #49 lateral contractor replaced 7 and 2
laterals and had to remove miscellaneous
concrete
5 Bid Item 12 Instead of replacing 4 of pipe contractor 2 600 00
Line #50 replaced 8 plus new wye and had to remove
miscellaneous concrete
6 Bid Item 16 Installed 8 of pipe instead of 4' 2 600 00
Line #74
7 Bid Item 17 Deleted from project Was repaired using (1 300 00)
Line #75 Link-Pipe
8 Bid Item 20 Installed 6 of pipe new wye and 1 300 00
Line #98 reconnected lateral instead of 4 of pipe
9 Bid Item 21 Installed 8 of pipe a new wye and new 0 00
Line #108 cleanout instead of only 4' of pipe
Contractor not asking for extra work as
good faith gesture
10 Bid Item 23 Excavation was 12 deep instead of 7' 0 00
Line #110 Contractor not asking for extra work as
good faith gesture
11 Bid Item 24 Excavated down to pipe but could not (1 300 00)
Line #111 repair due to adjacent concrete encased
water valve box District will attempt
to fix with Link-Pipe
12 Bid Item 27 Deleted from project. Was repaired using (3 900 00)
Line #121 Link-Pipe
13 Bid Item 28 Installed 6 of pipe instead of 4 1 300 00
Line #123
Page 2
PROJECT 1112100-126 RECONSTRUCTING VARIOUS SEWER LINES
Change Order No 1 January 27 1994
Bid Item Description of Work Extra Work Amount
14 Bid Item 31 Installed 7' of pipe, new wye and new 1 300 00
Line #136 lateral instead of 4' of pipe
15 Bid Item 32 Installed 20 of pipe instead of 4 6 900 00
Line #137 Problem caused by OCSD who will be
reimbursing CMSD for regular and extra
work portion of contractor's cost.
16 Bid Item 33 Installed 5 of pipe instead of 3 650 00
Line #138
Net increase in contract $13 400 00
6g,,S01T4.41 _
ANIL+P) $
COSTA MESA_ �'��f�x � °-�,, DISTRICT 54
_ _ y,!' p
_ DIRECTORS"
Costa Mesa Recycles
J �,' _ ww lames Wahner James
lary 28 1994 CORPOeA!3 Nate Rea eman
Arthur Perry
Mike Scheafer
TO FINANCE
FROM: ROBIN B HAMERS DISTRICT ENGINEER
RE 1ST PROGRESS PAYMENT
PROJECT 1112100-126 RECONSTRUCTING VARIOUS SEWER LINES
GRBAVAC CONSTRUCTION CO INC
Item Bid Description Quan Contract %Com Total
No Quan to date Price
1 LS R & R #1 LS $ 390000 0% $ 000
2 LS R & R #2 LS 2 60000 0% 000
3 L S R & R #10 L S 2 600 00 100% 2 600 00
4 LS R & R #20 LS 2 600 00 0% 000
5 L S R & R #21 L S 2 600 00 100% 5 850 00*
6 L S R & R #29 L S 1 950 00 0% 0 00
7 L S R & R #30 Deleted 2 600 00 0% 0 00*
8. LS R & R #33 LS 1 950 00 0% 000
9 L S R & R #43 L S 1 950 00 100% 2 600 00*
10 L S R & R #48 L S 3 900 00 100% 3 900 00
11 L S R & R #49 L S 2 600 00 100% 4 550 00*
12 L S R & R #50 L S 2 600 00 100% 5 200 00*
13 L S R & R #61 L S 2 600 00 0% 0 00
14 L S R & R #67 L S 1 300 00 100% 1 300 00
15 L S R & R #68 L S 3 900 00 100% 3 900 00
16 L S R & R #74 L S 2 600 00 100% 5 200 00*
17 L S R & R #75 Deleted 1 300 00 0% 0 00*
P.O. BOX 1200, COSTA MESA, CALIFORNIA 92628-1200 77 FAIR DRIVE (714) 754-5043
C' IT,g4
COSTA MESA A N DISTRICT
~ DIRECTORS
Costs Me+a Recycles �, fames Wahner lames re 04PoRA19 Nate Rea eman
PR�ECT 1112100-126 RECONSTRUCTING YARD ' SEWER LINES Arthur Perry
Page 2 Mike $cheater
Item Bid Description Quan Contract %Com Total
No Quan to date Price
18 L S R & R #76 L S 2 600 00 100% 2 600 00
19 L S R & R #82 L S 2 600 00 100% 2 600 00
20 L S R & R #98 L S 2 600 00 100% 3 900 00*
21 L S R & R #108 L S 2 600 00 100% 2 600 00*
22 L S R & R #109 L S 2 600 00 100% 2 600 00
23 L S R & R #110 L S 2 600 00 100% 2 600 00*
24 L S R & R. #111 L S 2 600 00 100% 1 300 00*
25 L S R & R #118 L S 6 500 00 0% 0 00
26 L S R & R #120 L S 1 950 00 0% 0 00
27 L S R & R #121 Deleted 3 900 00 0% 0 00*
28. L S R & R #123 L S 2 600 00 100% 3 900 00*
29 L S R & R #127 L S 3 900 00 100% 3 900 00
30 L S R & R #129 L S 2 600 00 100% 2 600 00
31 L S R & R #136 L S 2 600 00 100% 3 900 00*
32 L S R & R #137 L S 2 600 00 100% 9 500 00*
33 L S R & R #138 L S 1 950 00 100% 2 600 00*
Change Order No 1 100% adjusted in above
Amount earned $ 79 700 00
Less 5% retention 3 985 00
Amount earned less retention 75 715 00
Amount previously paid 0 00
NET AMOUNT DUE $ 75 715 00
till
ROBIN' ö HAMtRS
District Engineer
* See attached Change Order No 1
P.O. BOX 1200, COSTA MESA, CALIFORNIA 92628-1200 77 FAIR DRIVE (714)754-5043