Project 132 - Change Order - Grbavac - 1994-02-25 Costa Mesa Sanitary District
CONTRACT CHANGE ORDER NO 1
PROJECT 1112100-132 Reconstructing Various Sewer Lines
TO Grgo & Gordon Grbavac Construction Co. , Inc. Contractor
You are hereby directed to make the herein described changes from the plans and specifications, or do the
following work not included in the plans and specifications on the contract.
Note: This change order is not effective until approved pursuant to adopted District policy
Change Requested by Costa Mesa Sanitary District
Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work
at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only
such time as equipment is actually used and no allowance will be made for idle time.
The anticipated amount of pipe replacement for each individual spot
repair was based on reviewing the TV video taken from inside the line
In some cases the amount of damaged pipe seen from inside the line does
not reflect the total damage as seen after the line is uncovered For
instance, a hole in the pipe seen from the inside, may be in reality just
part of a lengthy section of cracked pipe, the cracks not having yet pene-
trated to the inside of the pipe to become visible during the TV inspection,
Therefore, the contractor must replace the entire damaged section Also
during some excavations unanticipated obstructions are present such as
other utilities or concrete. The amount of extra work on each location
was negotiated to reflect the actual circumstances. See attached infor-
mation for a detailed description of each location and the extra work
required.
Net Increase I xl Decrease ❑ in Contract $ 12,000.00
r
By reason of this order the time of completion will be adjusted as follows. None
Anus
Prepared by Robi B flamers Date 2/25/94
3
Approved by i �I l'r 7*� Date 2/25/94
Dis % Engin
Approved by District Manager 1j q J Date 2/25/94
Requlreppp Mete In st $1,000 mo
• Board approval also needed when increase in cost exceeds 2% of contract or $1,000 whichever is greater
We, the . rsigned Contractor, have given careful conside ation to the change proposed and hereby agree, if this proposal is approved,
that we .rovide all equipment,furnish all materials,except as-may otherwise be noted above,and perform all services necessary for the
work ab- -reified,and will accept as full payment therefor the pric shown above.
Date allted 2/25/94 Contractor Grgo & Gordon Grbavac Construction Co Inc
A 1A 11i�
B
y Title President
CMF 1082-68 White-Distr ct File Ca ry-Contr cto Copy'Pink-Fin Golde od-Engin
PROJECT 1112100-132 RECONSTRUCTING VARIOUS SEWER LINES
Change Order No 1 February 25 1994
Bid Item Description of Work Extra Work Amount
1 Bid Item 3 Installed extra 4 of pipe plus wye $ 2 400 00
Line #17
2 Bid Item 5 Installed extra 8 of pipe plus wye and 4 200 00
Line #36 3 of new lateral
3 Bid Item 8 Deleted from the project To be repaired (2,400 00)
Line #51 using Link-Pipe
4 Bid Item 10 Installed extra 7 of pipe plus 2 wyes 4 200 00
Line #53
5 Bid Item 11 Installed extra 2 of pipe plus wye 1 200 00
Line #54
6 Bid Item 12 Deleted from the project To be repaired (1 200 00)
Line #56 using Link-Pipe
7 Bid Item 14 Installed 5 of pipe instead of 4 600 00
Line #59
8 Bid Item 15 Installed 5 of pipe instead of 4 600 00
Line #65
9 Bid Item 17 Deleted from the project Was previously (2 400 00)
Line #74 repaired
10 Bid Item 21 Installed 9' of pipe plus new wye instead 3 600 00
Line #101 of 3' of pipe Water service was running
into sewer main and wye
11 Bid Item 22 Installed 8' of pipe instead of 6 1 200 00
Line #117
Net increase in contract $ 12 000 00
CMSD/#132