Project 133 - Proposal - Hamers - 1994-07-19 J) ROBIN B. HAMERS
234E 17TH ST SUITE 205
S. ASSOCIATES, INC. COSTA MESA,CA 92627
CIVIL ENGINEERS PLANNERS SURVEYORS (714?54B-1192
July 19 1994
Board of Directors
Costa Mesa Sanitary District
P 0 Box 1200
Costa Mesa CA 92628
RE PROPOSAL TO PROVIDE INSPECTION SERVICES
PROJECT 1112100-133 PUMP STATION MAINTENANCE
Gentlemen
The following proposal is submitted to provide the necessary
engineering services during the construction phase of said
project
Construction is scheduled to be completed within a 9 week period
beginning in September 1994 The necessary services to oversee
the project are engineering drafting and inspection and the
estimated maximum number of hours and proposed rate for each are
as follows
Engineering 40 hrs @ $59 00/hr = $ 2 360 00
Drafting 4 hrs @ $47 00/hr = 188 00
Inspection 150 hrs @ $42 00/hr = 6 300 00
TOTAL $ 8 848 00
The above are maximums and billing will be only for actual time
worked
Sincerely
R
Robin B Hamers
RBH/jp/proposal cms