Change Order - Casada Construction - 1996-04-01 Costa Mesa Sanitary District
CONTRACT CHANGE ORDER NO 1
PROJECT #139 Congress Pumping Station Abandonment
TO Steve Casada Construction Co Contractor
You are hereby directed to make the herein described changes from the plans and specifications, or do the
following work not included in the plans and specifications on the contract.
Note: This change order is not effective until approved pursuant to adopted District policy
Change Requested by Steve Casada Construction Co
Description of work to be done, estimate of quantities and prices to be paid. Segregate between additional work
at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only
such time as equipment is actually used and no allowance will be made for idle time.
Contractor experienced general failure of the asphalt street surface
in the construction area and other adjacent areas necessitating
increased replacement paving The street surface was old worn and
dry with cracking Contractor also experienced a slightly sandy soil
in one area of the trenching causing him to modify his shoring method
and necessitating extra backfill material Contractor is requesting
$22 374 for additional asphalt paving and $31 568 for trench related
problems
Recommended negotiated total amount = $38 000
Net Increase ® Decrease ❑ in Contract $ 38,000 00
By reason of this order the time of completion will be adjusted as follows: No146
Robin B Hamers 4/1/96
Prepared by Date
Approved by Robin B Hamers Iktuk Date 4/1/96
District E e
•
Approved by District Manager Robin B. Hamers iut.v^ Date 4/1/96
Requ• ed who ncrease • c s s $1,000 mo
• Board approval also needed when increase in cost exceeds 2% of contract or $1,000, whichever is greater
We the undersigned Contractor, have-given careful consideration to the change proposed and hereby,agree, if this proposal is approved,
that we will provide all equipment,furnish all materials,except as may otherwise be noted above,and perform all services necessary for the
work above specified,and will acce t as full payment therefor the prices shown above. A �/
Date accepted �7 7� & Contractor above.
/(�/ .�4 C G
By .>C/'l�C%Y d:;I ez Title C ex r
At'rtzovw QY tho1 w o
CMF 1082-68 White-Oistr ct File.Ca ry-Contr cto Copy- Pink.Fi Golde od-Engin Di ize iva5 4/17/94,
SticSteve Coscid° Construction Co.
1426 S. Allec Street * Anaheim, CA 92805
(714) 991-8350 license #528669
March 28 , 1996
Costa Mesa Sanitary District
RE Congress Pump Station Abandonment
ATTN Robin Hamers
Dear Robin
The following is a very conservative estimate of the
additional cost that Casada Const is going to incur due to
the excess width of the trench and the additional paving
From station 2+00 to station 7+75= 575 Lf For the excavation
of the trench it took an additional two days for labor and
equipment
Foreman 16 hrs x 55 00 per hr - $880 00�
Operator 16 hrs x 46 00 per hr - $736 00
(5) Labors 16 hr ea =80hrs x 38 00 per hr- $3 040 00
235 Excavator 16 hrs x104 00 per hr - $1 664 00
950 Loader 16 hrs x44 00 per hr - $704 00
Crew Truck & Tools 150 00 per day- $300 00
Material From station 2+00 to station 7+75
575 Lf x8 x11 5= 2 938 tons of base x 8 00- $23 504 00
Minus normal trench of 575 x 2x 11 5=734 ton x8 00=$5 872 00
Additional cost for base material=---$17,632 00
Exported 2 938 tons x 3 00 per ton- $8 814 00
Less 575 Lf x 2 'x 11 5=734 tons x 3 00- $2 202 00
Additional Cost exported materials- $6 612 00
c
Asphalt
State St 2 142 Sf x 1 60 per Sf - $3 427 00
State St Beyond trench 2, 735 Sf x 1 60 Sf - $4, 376 00
Congress Street 14, 295 Sf x 1 60 Sf - $22 872 00
Normal Paving of sewer trench was figured at,
1297 Lf x 4 = 5, 188 Sf x 1 60 Sf - $8, 300 80
Additional Cost for Asphalt- $22 374 00
My total estimated additional Cost for job
$53 942 00