Project 146 - Proposal - Hamers - 1995-12-27 5)
ROBIN B. HAMERS
234 E 17TH ST SUITE 205
& ASSOCIATES, INC. COSTA MESA,CA 52627
CIVIL ENGINEERS PLANNERS SURVEYORS [7141546-1192
December 27 , 1995
Board of Directors
Costa Mesa Sanitary District
P 0 Box 1200
Costa Mesa, CA 92628
RE PROPOSAL TO BEGIN PROJECT
PROJECT 1112100-146 TELEVISING SEWER LINES
Dear Board of Directors
Previously, four large phases of televising projects were
completed over a four year period covering the majority of the
District's sewer mains and the results of the televising have
become the foundation for determining the schedule for
maintenance and rehabilitation of the sewer system After the
four large projects, the third of a series of small yearly
projects was authorized and is ,nearing completion
This project , as shown in the 1995-96 Capital Improvement
Program is the fourth in the series of small yearly projects, and
will achieve the following results
1 By limiting the televising to less than $5, 000 per year the
project does not have to be bid The District can select
its own contractor which will be the contractor who was the
low bidder and completed the four large televising projects
This will provide continuity in record keeping and
efficiency in completing the work since the contractor is
familiar with the system
2 The District receives frequent calls from homeowners who
believe tree roots in the District's main line are causing
stoppages in their laterals By having the televising
contractor working on a regular basis throughout the
District the contractor can easily include areas where there
is a potential dispute
3 Certain areas need to be re-televised to check the
structural condition of the pipe and to determine the
effectiveness of the root cutting and foaming
4 There are some areas that have not yet been televised and
these areas will be a part of the proposed small yearly
televising projects
Si.
t: Printed on Recycled Paper
Board of Directors
December 27, 1995
Page 2
The project appropriation as shown in the 1995-96 Capital
Improvement Program is as follows
Design $ 2 500
Televising Cost 5 000
Inspection 3 500
Reserve 1, 000
TOTAL $ 12 000
It is recommended the Board authorize the televising to be
completed for less than $5, 000 and the Manager/District Engineer
to complete the design and inspection at the following hourly
rates not to exceed $2 , 500 and $3 500 respectively
Engineer $59 00/hr
Inspection $42 00/hr
Si cerely,
4,,u
Ro in B Hamers
RBH/jp/proposal cms
-` I 9 9 5 - 9C CAP tie roocifld
Project 1112100-146 •Televisina Sewer Lines
The project is an on-going yearly small scale 'pick-up' project
where it is proposed to televise areas not previously televised
or to re-televise areas needing to be rechecked It is proposed
to limit the televising cost to less than $5 000 to be able to
select the same contractor who was the low bidder on the original
four large televising projects that televised the majority of the
District's main lines The contractor could then be hired under
a purchase order This will insure continuity in the District's
record keeping
Some of the benefits of having an on-call contractor are to
settle potential disputes with homeowners as to whether sewer
line stoppages are in the laterals or in the main line as well as
checking the effectiveness of foaming and root cutting and
checking the structural condition of the pipe
The design portion of the project encompasses preparing maps and
schedules for the contractor Preparing the maps includes
reviewing previous televising projects to determine areas
requiring re-televising plus including portions of the system not
yet televised The previously used area and manhole designation
system is used and expanded to allow coordination of the new and
old information Inspection consists of monitoring the
District' s cleaning forces schedule, since the District must
clean the lines immediately prior to televising, as well as being
present during the televising operation The televising cost is
estimated at 11, 000 feet of pipe at $0 45 per foot
An estimate of the project costs is as follows
Design $ 2 , 500
Televising Cost 5, 000
Inspection 3 , 500
Reserve or Contingency 1, 000
TOTAL $12 000
- 6 -
it J.
Mr Robin Hamers August 29 1995
Page 2
Project 112100-145 Reconstructing Various Sewer Lines
This project is similar to previous years projects and in keeping with the District s rehab and
maintenance program.
Previous years projects were Nos. 122, 126, 132 and 140.
This project will utilize Link-Pipe or remove and replace construction techniques depending
upon conditions found after further investigation.
The construction budget will allow for repairs at approximately 35 locations. Based on data
provided, cost could range from $650 to $700 per foot, pending type of construction used.
Because of numerous locations the design, inspection and contingency budget appears to be
reasonable.
Project 1112100-146 Televising Sewer Lines
As discussed for previous CIP programs and with District staff this is a service type project
not construction. Therefore, normal design, construction and inspection percentages do not
apply Project description, reasoning of need and approval were presented well.
The estimated televising costs represents approximately 11,000 feet of pipe to be televised at
S.45/1f based on discussions with District staff
Because of the nature of the project and that District staff is needed at all times for cleaning
ahead of the camera, coordination, and supervision of the work. the District Engineer costs
will be higher, percentage wise, versus a design project.
It is noted that suggestions from 1994-95 were incorporated in this year s CIP program.
Project 1112100-147 Update Early Warning System Protecting Pumps
Recent completed projects utilized pumps containing the latest sensing mechanisms.
This project will modify existing pumps to provide similar telemetry for sensing moisture
and heat.
This is the first of several projects which will update pump telemetry over a three to five year
period.
For budgeting purposes the design, construction inspection and contingency costs appear
reasonable.
As a suggestion for future projects, the use of a map (Thomas Bros) showing proposed
locations would be beneficial.