Project 147 - Proposal - Hamers 1996-07-01 ROBIN B HAMERS 234 E 17TH ST SUITE 205
& ASSOCIATES INC. COSTA MESA. CA 92627
CIVIL ENGINEERS • PLANNERS • SURVEYORS (7143 54B- 92
FAX 714) 549-6516
July 1 1996
Board of Directors
Costa Mesa Sanitary District
P 0 Box 1200
Costa Mesa CA
RE PROPOSAL TO COMPLETE PROJECT
PROJECT 1112100-147
UPDATE EARLY WARNING SYSTEM PROTECTING PUMPS
Dear Board of Directors
As described in the attached excerpt from the 1995-96 Capital
Improvement Program the project consists of installing heat and
moisture sensing relay systems in seven pumping stations and
installing new pumps with these same relays in four pumping
stations when the existing pumps reach their life expectancy
The pumps in these four stations are old and cannot accept the
relays The addition of the heat and moisture sensing relays
allows the pumps to be automatically shut down when the sensors
are triggered rather than having the pump continue running and
burn out
The project will be done in parts over a three to five year
period with the first portion being the installation of the
sensors in the existing .pumps Three or four of the stations
will be modified first to insure the equipment works properly and
integrates well with the electrical system then the equipment
will be installed in the remaining stations
The project will most likely be done under a series of purchase
orders rather than being put out to bid The sensors will be
done in two phases the first few stations on a trial basis for a
total cost of less than $10 000 then a year or so later the
remaining stations will be done at a total cost of less than
$10 000 Pump replacement with new pumps containing the
sensors will be done on an as-needed basis as the existing pumps
reach their life expectancy Replacing pumps in this fashion is
more of a maintenance project than a capital project.
The estimated purchase/installation/construction cost for the
project is $65 000 As shown in the capital improvement program
it is proposed to complete both the design phase and inspection
phase over the life of the project at the following hourly rates
not to exceed $9 500 for design and $9 500 for inspection
Engineer $ 63 00/hr
Draftsman 47 00/hr
Inspector 42 00/hr
La Printed on Recycled Paper
Board of Directors
July 1 1996
page 2
The design phase consists of site visits to each pumping
station meeting with the manufacturers of the various equipment
reviewing specifications drawing plans and specifications
showing the installation of the equipment at each station and
issuing purchase orders for the work The inspection phase
consists of scheduling the work reviewing shop drawings for the
equipment and inspecting the installation
Si erely
//Julia.
Robin B Hamers
RBH/a proposal
( 9 95-- 96 Cko)rn- jce P,zo attair (-riot-,2Ar(
Project 1112100-147
u
Update Early Warning System Protecting Pumps
Recently the District completed Project #133 , Pump Station
Maintenance that included replacement of pumps in the Adams and
23rd Street pumping stations with the District preferred Flygt
pumps Previous to that the stations had pumps from a different
manufacturer The new Flygt pumps contain the latest sensing
mechanisms that, with the proper electrical equipment, will
provide a better warning system against pump burnout This
sensing and relay system otherwise known as telemetry is the
front line protection and most important component of the
electrical system
The most important feature of the telemetry system is the
moisture and heat sensors which will automatically shut down the
pumps if moisture has passed beyond the first set of seals or if
the temperature rises too high Other features include the
ability to respond to voltage changes such as if one leg of the
Edison three phase power becomes too low Since the cost of
replacement pumps is very high compared to the cost of installing
updated telemetry, the project is warranted
Currently four stations Adams 23rd Elden, and 21st have the
updated telemetry installed and operating and require no changes
Seven stations have Flygt pumps that can be modified to accept
the telemetry at a reasonable cost of approximately $2 000 per
station Four stations have Flygt pumps that will not accept the
telemetry so it is proposed to upgrade the telemetry when the
current pumps have reached their life expectancy and are replaced
with newer models Since the remaining life of these pumps
varies it is proposed to complete this portion of the project
over a three to five year period The remaining six stations
either have pumps of a different manufacturer or are scheduled to
be abandoned as part of the District ' s long term west-side
abandonment program However since the abandonment program is
contingent on participation by the County Sanitation Districts of
Orange County (CSD) and CSD has been adversely affected by the
recent County of Orange bankruptcy filing, the downstream sewer
facilities proposed by them are no longer a priority Therefore,
the project includes investigation and installation of updated
warning systems where considered appropriate
- 7 -
An estimate of the project costs is as follows
Design $ 9, 500
Purchase/Installation/Construction 65, 000
Inspection 9 , 500
Reserve or Contingency 16, 000
TOTAL $ 100, 000
- 8 -
00y1,-E \10I MEND Nei R poC
Mr Robin Hamers August 29 1995
Page 2
Project 112100-145 Reconstructing Various Sewer Lines
This project is similar to previous years projects and in keeping with the District's rehab and
maintenance program.
Previous years projects were Nos. 122, 126, 132 and 140
This project will utilize Link-Pipe or remove and replace construction techniques depending
upon conditions found after further investigation.
The construction budget will allow for repairs at approximately 35 locations. Based on data
provided, cost could range from $650 to $700 per foot, pending type of construction used.
Because of numerous locations the design, inspection and contingency budget appears to be
reasonable.
Project 1112100-146 Televising Sewer Lines
As discussed for previous CIP programs and with District staff this is a service type project
not construction. Therefore. normal design. construction and inspection percentages do not
apply Project description, reasoning of need and approval were presented yell.
The estimated televising costs represents approximately 11 000 feet of pipe to be televised at
$ 45/lf based on discussions with District staff
Because of the nature of the project and that District staff is needed at all times for cleaning
ahead of the camera. coordination, and supervision of the work, the District Engineer costs
will be higher. percentage wise, versus a design project.
It is noted that suggestions from 1994-95 were incorporated in this years CIP program.
Project 1112100-147 Update Early Warning System Protecting Pumps
Recent completed projects utilized pumps containing the latest sensing mechanisms.
This project will modify existing pumps to provide similar telemetry for sensing moisture
and heat.
This is the first of several projects which will update pump telemetry over a three to five year
period.
For budgeting purposes the design, construction inspection and contingency costs appear
reasonable.
As a suggestion for future projects, the use of a map (Thomas Bros) showing proposed
locations would be beneficial.