Project 168 - Proposal - Hamers 2007-06-11 ROBIN B. HAMERS & ASSOC., INC. 234 E. 17TH ST SUITE 205
CIVIL ENGINEERS PLANNERS SURVEYORS COSTA MESA, CA 92627
since 1981 Phone 949/548-1192
Fax 949/548-6516
June11 2007
BOARD OF DIRECTORS
COSTA MESA SANITARY DISTRICT
628 W 19`h Street
Costa Mesa, CA 92627
RE. CMSD #168 Irvine Pumping Station Relocation
Proposal to Provide Construction Inspection Services
Dear Board Members.
The construction of the new Irvine Pumping Station represents the largest capital
improvement project undertaken by the Costa Mesa Sanitary District with a
construction cost of over $1 7 million The new pumping station will be
constructed over a three month period beginning August 1 2007 and will be
completed prior to the County of Orange construction of the Irvine Avenue
widening project.
The relocation of the pumping station was necessitated by the road widening
project. Agencies owning pipelines and other facilities in a street must bear the
relocation costs when the road is realigned.
The successful construction and long life expectancy of the pumping station is
based mainly on two factors the contractor's ability and continuous inspection
and engineering provided by the District. There are significant amounts of shop
drawing review and other engineering requirements inherent in pumping station
construction. Therefore the following proposal is submitted and is an hourly
proposal based on a maximum number of possible hours.
Engineering 24 weeks x 16 hrs/week x $ 85/hr = $32,640
Surveying 20 hrs x $220/hr = $ 4 400
Inspection 75 days x 8 hrs/day x $60 00/hr = $36,000
TOTAL $73 040
It should be noted that the above services are usually budgeted at 10% of the
construction costs, which in this case is 10% of $1 7 million or $170 000
The above budget is a maximum and billing will only be for actual time worked
Thank you
Sincerely
ROBIN B HAMERS
Registered Civil Engineer
RCE 31720