Costa Mesa HQ Landscaping Renovation Schedule 10-09-23-IPID WBS Task NameDurationStartFinish11Costa Mesa Sanitary District - #342 HQ Landscaping Renovation129 daysMon 7/24/23Mon 1/29/2421.1Notice of Award0 daysMon 7/24/23Mon 7/24/2331.2Contract to Completion ‐ 75 Working Days75 daysTue 10/10/23Mon 1/29/2441.3Pre‐‐Construction Planning Tasks55 daysMon 7/24/23Tue 10/10/2351.3.1Prepare and Submit Contracts / Insurance / Bonds30 daysMon 7/24/23Fri 9/1/2361.3.2Develop Tentative Construction Schedule 12 daysTue 9/5/23Wed 9/20/2371.3.3Schedule Pre‐Construction Meeting with Subs12 daysTue 9/5/23Wed 9/20/2381.3.4Pre‐Construction Meeting1 dayFri 9/22/23Fri 9/22/2391.3.5Prepare Notice to Proceed0 daysWed 10/4/23Wed 10/4/23101.3.6Anticipated Construction Start Date0 daysTue 10/10/23Tue 10/10/23111.4Mobilization and Pre‐Construction Requirements1 daysMon 10/10/23Mon 10/10/23121.4.1Tree Removal3 daysTues 10/10/23Thur 10/12/23131.4.1.1Tree Removal3 daysTue 10/13/23Thur 10/12/23141.4.2Mobilization1 dayMon 10/16/23Mon 10/16/23151.4.2.1Storage Container/Restroom/Fence Move In 1 dayMon 10/16/23Mon 10/16/23161.5Site Prep22 daysMon 10/16/23Thu 11/16/23171.5.1Site Preparation and Grow and Kill3 daysMon 10/16/23Fri 10/20/23181.5.2Gopher Hole Extermination - ???1 dayMon 10/23/23Mon 10/23/23191.5.3Remove Shrubs/Landscaping/Misc3 daysTue 10/16/23Fri 10/20/237/241/29Costa Mesa Sanitary District - #342 HQ Landscaping Renovation7/24 7/24Notice of Award10/101/29Contract to Completion - 75 Working Days7/2410/10Pre--Construction Planning Tasks7/249/1Prepare and Submit Contracts / Insurance / Bonds9/5 9/20Develop Tentative Construction Schedule 9/5 9/20Schedule Pre-Construction Meeting with Subs9/22 9/22Pre-Construction Meeting10/410/10 10/10Anticipated Construction Start Date10/13 10/17Mobilization and Pre-Construction Requirements10/13 10/17Tree Removal10/13 10/17Tree RemovalMobilization10/16 10/16Storage Container/Restroom/Fence Move In 10/1611/16Site Prep10/1610/20Site Preparation and Grow and Kill10/1610/20Gopher Hole ExterminationRemove Shrubs/Landscaping/Misc 10/23 10/23MayJunJulAugSepOctNovDecJanFebQtr 2, 2023Qtr 3, 2023Qtr 4, 2023Qtr 1, 2024TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineCriticalCritical SplitProgressManual ProgressPage 1Project: Costa Mesa Project SchDate: Mon 10/9/23 ID WBS Task NameDurationStartFinish201.5.4Earthwork/Grading6 daysFri 10/27/23Fri 11/3/23211.5.5Driveway Removal1 dayMon 11/6/23Mon 11/6/23221.5.6Install Drainage8 daysTue 11/7/23Thu 11/16/23231.6Irrigation20 daysFri 10/27/23Mon 11/27/23241.6.1Domestic Meter Backflow5 daysFri 10/27/23Thu 11/2/23251.6.2Install All Irrigation Mainlines and Laterals20 daysFri 10/27/23Mon 11/27/23261.7Electrical Work (Pending Approved Submittal)18 daysMon 11/13/23Fri 12/8/23271.7.1Electrical Work Sub18 daysMon 11/13/23Fri 12/8/23281.7.2Panel D Installation3 daysWed 12/6/23Fri 12/8/23291.8Landscaping / Hardscape30 daysTue 11/13/23Fri 12/15/23301.8.1Install Hardscape per Plan15 daysMon 11/13/23Tue 12/05/23311.8.2Landscape per Plan15 daysTue 11/28/23Fri 12/15/23321.9Close Out4 daysFri 12/22/23Thu 12/28/23331.9.1Punchlist Items2 daysFri 12/22/23Tue 12/26/23341.9.2Demobilizaion2 daysWed 12/27/23Thu 12/28/23351.9.3Begin Maintenance Period0 daysThu 12/28/23Thu 12/28/2310/27 11/3Earthwork/Grading11/6 11/6Driveway Removal11/7 11/16Install Drainage10/2711/27Irrigation10/27 11/2Domestic Meter Backflow10/2711/27Install All Irrigation Mainlines and Laterals11/1312/8Electrical Work (Pending Approved Submittal)11/1312/8Electrical Work Sub12/6 12/8Panel D Installation12/15Landscaping 11/13/ Hardscape11/2812/15Install Hardscape per Plan 11/13 12/15Landscape per Plan12/22 12/28Close Out12/22 12/26Punchlist Items12/27 12/28Demobilizaion12/28 12/28Begin Maintenance PeriodMayJunJulAugSepOctNovDecJanFebQtr 2, 2023Qtr 3, 2023Qtr 4, 2023Qtr 1, 2024TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineCriticalCritical SplitProgressManual ProgressPage 2Project: Costa Mesa Project SchDate: Mon 10/9/23 1Costa Mesa Sanitary District - #342 HQ Landscaping RenovationEnclosed please find our CPM schedule for the project.Except for contractual completion requirements, the duration times for the various items of work shown on the enclosed CPM schedule are estimates only and not commitments. They are based on presently known or represented conditions and any changes therein will require a change in schedule. Please note specifically those items of work which are placed by or dependent upon actions by the Owner or those under his control, since we are relying on being able to commence and proceed with those activities on the dates shown and any delays of that nature would affect our schedule.We will assume that this schedule is acceptable to you and in conformance with our contract requirements unless we hear from you to the contrary within Three working days.Page 3