#321 Indus Sewer Main Replacement - Bond Release
Costa Mesa Sanitary District
….an Independent Special District
November 12, 2019
Developers Surety and Indemnity Company
17771 Cowan,
Suite 100,
Irvine, CA 92614
Project: #321 Indus Sewer Main Replacement
Gentlemen:
The above project was completed on October 16, 2019, therefore, the following bond is
exonerated 35 days after the date the notice of completion is recorded.
Labor and Material Bond No. 367476P - $267,040.00
The following bond is exonerated one year from the date the notice of completion is recorded.
Faithful Performance Bond No. 367476P - $267,040.00
Therefore, unless you are notified otherwise, the Labor and Material Bond is exonerated as of
December 21, 2019, and the Faithful Performance Bond is exonerated as of October 16, 2020.
Sincerely,
Robin B. Hamers
District Engineer
(714) 293-2727
Cc: Gentry General Engineering, Inc.
Clerk of the District