Bond Release - GCI Construction Inc. - 2017-03-19
March 29, 2017
International Fidelity Insurance Company
2400 E. Katella Avenue, Suite 250
Anaheim, CA 92806
RE: Project #202 Elden Pump Station Valve and Piping Replacement
Gentlemen:
The Board of Directors of the Costa Mesa Sanitary District at their regular meeting of March 23, 2017, accepted the project as completed and ordered the following bond exonerated
35 days after the Notice of Completion is recorded:
Labor and Material Bond No. 0608928 - $259,300
The Board also ordered the following bond exonerated one year from the date of recording of the
Notice of Completion.
Faithful Performance Bond No. 0608928- $259,300
Unless you are notified otherwise, the Labor and Material Bond is exonerated as of May 2, 2017 and the Faithful Performance Bond is exonerated as of March 28, 2018.
Attached is a copy of the recorded Notice of Completion.
Sincerely,
/
Robin B. Hamers
District Engineer
Encl.
Cc: GCI Construction, Inc.
Clerk of the District