Minutes - Sewer System - 2010-04-13CJ
COSTA MESA SANITARY DISTRICT
MINUTES OF SEWER SYSTEM COMMITTEE MEETING
APRIL 13, 2010
CALL TO ORDER Board members of the Costa Mesa Sanitary District
met in Committee session on April 13, 2010 at 10:30
a.m. at 628 W. 19th Street, Costa Mesa.
Director Monahan called the meeting to order at
10:40 a.m.
DIRECTORS PRESENT: Gary Monahan, Art Perry, Bob Ooten, Jim Ferryman
STAFF PRESENT: Scott Carroll, General Manager, Thomas A. Fauth,
Operations Manager; Sherry Kallab, Administrative
Manager; Rob Hamers, District Engineer; Karl
Dulake, Maintenance Supervisor; Debbie Bjornson,
Permit Processor; Paul Guzman, Inspector
OTHERS PRESENT:
MONTHLY SSO STATISTICS
Mr. Fauth reported no spills occurred since October 20, 2009.
POTENTIAL PERFORMANCE INDICATORS FOR JUDGING AGENCY SPILLS
A handout was provided in the Committee packet reviewing potential measures for identifying
spills. Mr. Hamers reported once every three years there is a review of the Waste Discharge
Requirements (WDR), both of the WDR itself and of the monitoring /reporting requirements. The
monitor /reporting members make up the data review committee and the data review committee
provided the potential performance indicators. The committee understands the number of spills
per hundred miles is not the best indicator and has little correlation to the spill volumes. The
information in the potential indicators is from actual data on spills and volumes of spills from
January 2006 to January 2010 statewide. The committee is evaluating the data as a replacement
to the spills per hundred miles indicator. Director Ooten noted at least ten people are looking at
the same data sets to determine a good indicator. The data does show the significance of roots
• at the facility. Mr. Hamers estimated the tri- annual review should be completed by July or August
2010. Mr. Hamers will schedule a follow -up inflow reduction meeting.
psagrr�8 COSTA MESA SANITARY DISTRICT
MINUTES OF BOARD OF DIRECTORS SEWER SYSTEM COMMITTEE MEETING
'+1) APRIL 13, 2010
r
.. �$➢' • ' —1�, PAGE 2
aaa's�5'
SANTA MARGARITA WATER DISTRICT (SMWD) FORCE MAIN SPILL
The Committee reviewed photographs taken of the Santa Margarita force main spill. Mr. Fauth
reported a nearby creek was used as a containment vessel for the spill. The force main pipe was
24 inch. Lessons learned are forthcoming. The WDR Steering Committee is following up on the
details. Mr. Hamers noted the pipe was only twenty years old which means something wasn't
designed or inspected properly when installed; a ductile iron pipe (DIP) force main should not
wear out in twenty years. If there is an error in installation, corrosion can cause damage very
quickly. Santa Margarita did try to use other agency's pumper trucks, emergency response,
personnel, etc. There were not enough assets in the area. At peak flow it was impossible for all
the trucks to vacuum the spill - it was flowing so heavily and they had to keep pumping it into the
creek to contain the spill. During low flow they were able to vacuum it out and drive it down to the
other side of the force main and pump it into downstream manholes. Communication was also a
problem in terms of when will the break be fixed, what is the spill volume, who do we contact,
where do other agency's responders get gas, food and water. Mr. Hamers is not sure of the
actual spill volume but has heard 900 thousand gallons. CMSD has an 18 inch force main that
carries 3,850 gallons per minute so with a 24 inch force main it was probably between four and
five thousand gallons per minute. It took days to find the problem and days to fix because it was
on a slope and that kind of pipe had to be specially coated. Mr. Guzman reported on two
significant CMSD spills in prior years and noted technology is not perfected to determine the
condition of a force main pipe.
0 ASSET MANAGEMENT
A seminar handout was provided in the Committee packet. Mr. Carroll and Mr. Fauth signed up
to attend the April 21St and 22nd seminar. To piggyback on this workshop, Staff invited Brown &
Caldwell to give a demonstration of their approach to asset management. Mr. Carroll noted
Brown & Caldwell is a main player in asset management. Brown & Caldwell prepared the asset
management plan study for the Orange County Water District, Irvine Ranch Water District, and
Santa Margarita Water District. Staff will recommend an approach to the Committee. Director
Ooten recommended Staff also talk to GHD.
EAST BAY MUNICIPAL UTILITY DISTRICT ( EBMUD) PRIVATE LATERAL
PROGRAM
Mr. Fauth reported the EBMUD sewer lateral assistance program is going into effect. Mr. Hamers
added they are under an EPA order due to poor sewer system management. The EPA order
included private laterals. EBMUD's annual budget for the new program is $2 million per year.
CMSD INFLOW REDUCTION PROGRAM
The Inflow Reduction Subcommittee met on March 26, 2010 and the handout packet included a
set of the meeting minutes. Director Ooten reported the Committee discussed sealing and
plugging of manholes and an analysis of the data available to date. The District's efforts appear
to have had an effect on OCSD's storm peak flow numbers - down significantly. Mr. Hamers is
continuing to gather more data regarding rainfall and rainfall patterns. All Subcommittee
members were assigned tasks and will meet one more time this season to set up the plan of
•
COSTA MESA SANITARY DISTRICT
5ANlfq
MINUTES OF BOARD OF DIRECTORS SEWER SYSTEM COMMITTEE MEETING
APRIL 13, 2010
'srP$ooeAt'�° PAGE 3
attack for the next rainy season. Mr. Hamers reported the WDR Inflow and Infiltration Surveys
have been returned and data from those survey results will be available.
CMSD MAP UPGRADES /GIS /CMMS UPDATES
Mr. Fauth .informed the Committee the last portion of phase one will be complete once EEC
receives the last few maps back from CMSD Staff. Staff authorized EEC to proceed to phase
two. Mr. Fauth pointed out sections of the District with lines remaining to be cleaned to meet the
three -year industry cleaning standard. Staff finalized the maps yesterday and meets with
National Plant Services at 2:00 pm today to review. Mr. Fauth estimates it will take two months to
complete the next 400 thousand linear feet using a three -man crew and two Vactor trucks.
SCADA UPGRADE STATUS
Mr. Fauth stated the project is for the most part complete. Staff worked with the City of Newport
Beach personnel and arranged to have the trees around the 23rd Street pump station cleared to
allow for the new antenna to be installed. The only station left to complete is the District Yard.
Mr. Fauth has requested a copy of the relay plan from TRC.
CMSD SEWER CLEANING /CCTV PROGRAM - UPDATE
This item was discussed under CMSD Map Upgrades.
WDR TRAINING SEMINAR 6 -17 -10 "TREE ROOTS IN SEWERS"
Mr. Hamers reported the May seminar was delayed until June due to a conflict with another
conference. The "Tree Roots In Sewer" seminar is now scheduled for June 17, 2010 from 9:30
till 11:30.
CMSD PROJECTS:
PROJECT #129 — BRISTOL STREET SEWER PROJECT
Staff is currently meeting with contractors to determine the feasibility of pipe bursting the
remaining one third of the sewer.
PROJECT #171 — IRVINE PUMPING STATION FORCE MAIN
Staff is meeting with lining and slip lining contractors to determine the best method to rehabilitate
the line. The condition assessment is contained in a Staff report to the Board and will be in the
next Board packet. Mr. Hamers recommended the Committee discuss the project more in depth
after the Board has reviewed the report.
a �e
COSTA MESA SANITARY DISTRICT
MINUTES OF BOARD OF DIRECTORS SEWER SYSTEM COMMITTEE MEETING
, APRIL_ 13, 2010
l l`°QPa_ea'A° PAGE 4
PROJECT #186 — SEWER LATERAL ASSISTANCE PROGRAM
Mr. Fauth reported $104,000 has been spent this fiscal year. Seventy eight projects have been
completed, thirty eight are in process and one is waiting for review as of last week. The trend is
cyclical and the reason is undetermined. Director Ooten requested Staff provide a multi -year
report showing applications and completed projects..
PROJECT #187— DISTRICT YARD
Mr. Hamers reported the District Yard project is progressing on schedule. Mr. Fauth reported the
flag pole base installation is in process. A gas sleeve needs to be put in place. Staff chose to go
with Mike Kilbride rather than the Gas company for a savings of $30,000. The contract for
security services will be in the form of the CMSD standard contract and is currently under review
with the company interface. Mr. Fauth reported bids were requested from four organizations and
three were unresponsive. Mr. Hamers reported the City of Costa Mesa received stimulus funds
plans to make street improvements on both the south and north side of Wilson Street. Staff
eliminated from the contractor scope removing the old drive approach, building the new drive
approach, new sidewalk and landscaping. Staff is working with the contractor to determine the
savings to the District. The improvements are expected to be completed within the next two
months. Mr. Carroll recommended waiting to hold the grand opening until the improvements are
complete. Mr. Dulake reported the office furniture will not be delivered until June 1, 2010. Mr.
• Fauth added the rebate for the solar panels is in process.
CCTV VEHICLE DEMO
The Committee attended a CCTV truck demonstration in the District Headquarters' parking lot.
Mr. Carroll reported there will be discussion during the May 20, 2010 preliminary budget meeting
regarding the purchase of a CCTV truck and other CCTV options. Director Ferryman asked if the
District would need to hire an operator if the CCTV truck is purchased. Mr. Hamers responded
most agencies use their own staff to operate the truck. Director Monahan requested Staff
prepare an analysis of purchasing a CCTV truck or trailer or contracting for the service. Staff
recommends a 10 -to -15 year interval for CCTV of the entire District sewer main lines. The CCTV
truck, if purchased, would be for CCTV of small portions of the lines rather than entire line
system. Director Monahan recommended bringing the analysis back to the Committee and after
review, determine if a special meeting is needed to discuss the item. Mr. Hamers added when
you go to the full CMMS sewer system management system Staff can take the data provided by
the CCTV equipment and assign what was televised directly to the line segments creating a
historical system management document.
OTHER
Staff reviewed a survey regarding illegal dumping of grease. District Staff did respond to the
survey. The District has so little to report CMSD responses were not in the report.
• SSC MEETING SCHEDULE
The next meeting is scheduled for Tuesday, May 18, 2009 at 10:30 a.m
� COSTA MESA SANITARY DISTRICT
MINUTES OF BOARD OF DIRECTORS SEWER SYSTEM COMMITTEE MEETING
APRIL 13, 2010
PAGE 5
• \ �POII
PUBLIC COMMENTS
There were no public comments.
ADJOURNMENT
Director Monahan adjourned the meeting at 12:02 p.m.
SE6ET RY'
is
0